Contract No: HK/2015/01 Wanchai
Development Phase II and Central Wanchai Bypass Sampling, Field
Measurement and Testing Works (Stage 3) Environmental
Permit no. EP-356/2009, Further Evironmental permit nos. fep-02/356/2009,
FEP-03/356/2009, Fep-04/356/2009 , Fep-06/356/2009, FEP-07/356/2009 and
Fep-08/356/2009 Monthly Environmental Monitoring & Audit Report
-
NOVEMBER 2017 -
|
CLIENTS: |
|
Civil Engineering and
Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point 181-185
Gloucester Road, Wanchai, H.K. Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
Certified
by: |
|
Raymond
Dai Environmental
Team Leader |
|
DATE: |
|
12 December 2017 |
|
|
2.2 Scope of the Project and Site
Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact
Personnel
3 Status of
Regulatory Compliance
3.1 Status of Environmental Licensing and
Permitting under the Project
5.2 Water quality monitoring Results
6.4 Review
of the Reasons for and the Implications of Non-compliance
6.5 Summary
of action taken in the event of and follow-up on non-compliance
7. Cumulative
Construction Impact due to the Concurrent Projects
9. Complaints, Notification of Summons and Prosecution
lIST OF TABLES
Table I Summary of Water Quality Monitoring Exceedances in
Reporting Month
Table II Summary of Enhanced Dissolved Oxygen Monitoring
Exceedances in Reporting Month
Table 2.1 Schedule
2 Designated Projects under this Project
Table 2.2 Details of Individual Contracts under the Project
Table 2.3 Contact Details of Key Personnel
Table 3.2 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2009/01
Table 3.3 Summary of submission status under FEP-02/356/2009
Condition
Table 3.4 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2009/02
Table 3.5 Summary of submission status under FEP-03/356/2009
Condition
Table 3.6 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/15
Table 3.7 Summary of submission status under FEP-04/356/2009
Condition
Table 3.8 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/19
Table
3.9 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2012/08
Table
3.10 Summary of submission
status under EP-356/2009 & FEP-06/356/2009 Condition
Table
3.11 Cumulative Summary of
Valid Licences and Permits under Contract no. HY/2010/08
Table
3.12 Summary of submission
status under EP-356/2009 and FEP-07/356/2009 Condition
Table 4.1 Noise Monitoring Station
Table
4.2 Air Monitoring Station
Table 4.3 Marine
Water Quality Stations for Water Quality Monitoring
Table 4.4 Marine
Water Quality Monitoring Frequency and Parameters
Table 4.5 Marine
Water Quality Stations for Enhanced Water Quality Monitoring
Table 5.1 Noise
Monitoring Station for Contract nos. HK/2009/01, HK/2009/02
Table 5.2 Noise
Monitoring Station for Contract no. HY/2009/15
Table 5.3 Noise
Monitoring Station for Contract no. HY/2009/19
Table 5.4 Noise Monitoring Station for Contract
no. HY/2010/08
Table
5.5 Air Monitoring Station for Contract no.
HK/2009/01
Table 5.6 Air
Monitoring Station for Contract no. HK/2009/02
Table 5.7 Air
Monitoring Station for Contract no. HY/2009/15
Table 5.8 Air
Monitoring Stations for Contract no. HY/2009/19
Table 5.9 Air
Monitoring Stations for Contract no. HK/2012/08
Table 5.10 Air
Monitoring Stations for Contract no. HY/2010/08
Table 5.12 Water
quality monitoringStations for Contract no. HK/2009/01
Table 5.13 Water
quality monitoringStations for Contract no. HK/2009/02
Table 5.14 Water quality
monitoringStations for Contract no. HK/2012/08
Table 5.15 Water quality monitoring Station for Contract no. HY/2010/08
Table 5.16 Enhance Dissolved Oxygen Monitoring Stations for
Contract no. HY/2010/08
Table 5.17 Details
of Waste Disposal for Contract no. HK/2009/01
Table 5.18 Details of Waste Disposal for Contract no. HK/2009/02
Table 5.19 Details
of Waste Disposal for Contract no. HY/2009/15
Table 5.20 Details
of Waste Disposal for Contract no. HY/2009/19
Table 5.21 Details of Waste Disposal for Contract
no. HK/2012/08
Table 5.22 Details of Waste Disposal for Contract
no. HY/2010/08
Table 8.2 Summary of Environmental Inspections for Contract no.
HK/2009/02
Table 8.5 Summary of Environmental Inspections for Contract no. HK/2012/08
Table 8.6 Summary of Environmental Inspections for
Contract no. HY/2010/08
Table 9.1 Cumulative Statistics on Complaints
Table 9.2 Cumulative Statistics on Successful Prosecutions
Table 10.1 Construction
Activities and Recommended Mitigation Measures in Coming Reporting Month
lIST OF FIGUREs
Figure 2.2 Project Organization Chart
Figure 4.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix 5.1 Monitoring Schedule for Reporting Month and Coming month
Appendix 5.2 Noise Monitoring Results and Graphical Presentations
Appendix 5.3 Air Quality Monitoring Results and Graphical Presentations
Appendix 5.4 Water Quality Monitoring Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Summary for Notification of
Exceedance
Appendix 10.1 Construction Programme of Individual Contracts
EXECUTIVE SUMMARY
i.
This
is the Environmental Monitoring and Audit (EM&A) Monthly Report
– November
2017 for the Project of Wan Chai Development Phase II and Central-Wanchai Bypass
under Environmental Permit no. EP-356/2009 and Further Environmental permit
nos. FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009, FEP-06/356/2009, FEP-07/356/2009
and FEP-08/356/2009. This report presents the
environmental monitoring findings and information recorded during the period of 27 October 2017 to 26 November 2017. The cut-off date of reporting is at 26th
of each reporting month.
ii.
In
the reporting month, the principal work activities of individual contracts
conducted are as follow:
Contract no. HK/2009/01 – Wan Chai Development
Phase II – Central –Wanchai Bypass at HKCEC
Nil
Contract no. HK/2009/02 – Wan Chai Development
Phase II – Central – Wan Chai Bypass at Wan Chai East
·
Nil
Contract no. HY/2009/15 – Central-Wanchai Bypass –
Tunnel (Causeway Bay Typhoon Shelter Section)
·
Nil
Contract no. HY/2009/19- Wan Chai Bypass Tunnel
(North Point Section) and Island Eastern Corridor Link
Nil
Contract no. HK/2012/08 – Wan Chai Development
Phase II – Central- Wan Chai Bypass at Wan Chai West
Construction of Box 1 unit and
backfilling
Trimming of rock level
Contract no.
HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip Road 8)
Diversion pipe maintenance
Diaphragm wall removal works
Removal of reclamation at TS3E and TS3W
Removal of reclamation at TS3E and TS3W
Noise Monitoring
iii.
With respect to the shift in major construction
site portions at Wan Chai North, the noise monitoring station M1a – Harbour Sports
Centre was finely adjusted from East of Harbour Road Sports Centre to West of
Harbour Road Sports Centre on 21 June 2016.
iv.
With
respect to the demolition of Ex-Harbour Road Sports Centre, the respective
noise monitoring station M1a – Harbour Road Sports Centre were finely adjusted
on 16 and 25 May 2017 and thereafter to the Footbridge for Harbour Road Sports
for noise monitoring.
v.
Limit level exceedances were recorded at M1a – Footbridge for Harbour
Road Sports Centre on 03 and 22 November 2017 and the exceedances were
concluded as non-Project related.
vi.
Noise
monitoring during daytime and restricted hour were conducted at the stations M1a,
M2b, M3a, M4b, M5b and M6 on a weekly basis in the reporting month.
Air Quality Monitoring
vii.
One 1hr TSP action level exceedance was recorded at CMA5b – Pedestrian
Plaza on 01 November 2017 in the reporting month and the exceedance was
concluded as non-Project related.
viii.
Two 1hr TSP action level exceedances and one 1hr TSP limit level were
recorded at CMA5b – Pedestrian Plaza on 24 November 2017 in the reporting month
and the exceedance was concluded as non-Project related.
ix.
Due to electricity interruption, the TSP monitoring in the reporting
period are rescheduled as follow:-
The 24hr TSP monitoring at CMA3a was
rescheduled from 31 October 2017 to 01 November 2017.
The 24hr TSP monitoring at CMA4a was
rescheduled from 17 November 2017 to 18 November 2017.
The 24hr TSP monitoring at CMA5b was
rescheduled from 11 November 2017 to 13 November 2017.
x.
With respect to the proposed demolition of the Oil Street Site Office,
the respective air quality monitoring station CMA1b – Oil Street Site Office
was finely adjusted from the Oil Street Site Office to Harbour Grand Hotel
Boundary Wall from 05 June 2017 onwards.
xi.
With
respect to the proposed demolition of eastern podium of Oil Street Site Office,
the respective air quality monitoring station CMA1b – Oil Street Site Office
was finely adjusted from East podium of the Oil Street Site Office to the West podium
of the Oil Street Site Office on 21 December 2016.
xii.
1-hour
and 24-hour Total Suspended Particulates (TSP) monitoring were conducted at
CMA1b – Oil Street Site Office; CMA2a – Causeway Bay Community Center; CMA3a –
CWB PRE Site Office Area; CMA4a – Society for the Prevention of Cruelty to
Animals; CMA5b – Pedestrian Plaza; CMA6a – WDII PRE Site Office in the
reporting month.
Water Quality Monitoring
xiv.
Water
quality monitoring station C7 and Enhance DO monitoring station C6 shall be
associated with Contract HY/2010/08, upon confirmation of marine construction
works completion under Contract HY/2009/15 at CBTS area and Ex-PCWA area since
19 June 2017.
xv.
Referring
to CWB RSS confirmation on the completion of marine construction activities
within the Ex-PCWA area and the completion of the post construction water
quality monitoring, the respective Enhance DO Monitoring within Ex-PCWA for
monitoring station Ex-PCWA SE and Ex-PCWA SW was temporarily suspended since 07
March 2017 ebb tide onwards.
xvi.
With respect to the reinstatement of the silt screen system for Cooling
Water Intakes P7, P8, P9 and WSD Water Intake RW21, the respective water
quality monitoring was reverted to the previous monitoring location for Water
Quality Monitoring Station RW21-P789 from water quality stations RW21-P789 East
(RW21-P789E) and RW21-P789 West (RW21-P789W) from 25 January 2017 onwards.
xvii.
With
respect to the removal of silt screen at WQM station RW21-P789 on 26 November
2016, the respective water quality monitoring at RW21-P789 was adjusted to
RW21-P789E and RW21-P789W since 28 November 2016 ebb-tide.
xviii.
With
respect to the temporarily suspension of marine construction works at WCR3 Area
by Contract HK/2009/02, the installed silt screen for intake group (P7, P8, P9
and WSD21) was removed on 26 November 2016.
xix.
As
advised by the Contractor of HK/2009/01, all silt screen remains removal works
at P1, P3, P4, P5 and C1 water quality monitoring stations were completed on 8
May 2016.
xx.
With respect to the marine works undertaken at WCR3 by Contract HK/2009/02,
the respective water quality monitoring station C1 associated with Contract
HK/2009/01 was updated as in association with Contract HK/2009/01 and Contract
HK/2009/02.
xxi.
With respect to the marine works undertaken at CBTS by Contract
HY/2010/08, the respective water quality monitoring station C7 associated with
Contract HY/2009/15 was updated as in association with Contract HY/2009/15 and
Contract HY/2010/08.
xxii.
With respect to the marine works undertaken at HKCEC2 by Contract
HK/2012/08, the respective water quality monitoring station WSD19, P1, P3, P4,
and P5 were associated with Contract HK/2012/08.
xxiii.
As confirmed by WDII RSS, the marine construction works under Contract
HK/2009/01 have been completed since 24 July 2017, the monitoring association
with Contract HK/2009/01 and relevant reporting has been ceased in the
reporting month.
xxiv.
As confirmed by CWB RSS, the marine construction works under Contract
HY/2009/15 and relevant reporting have been completed by 19 June 2017, the
monitoring association with Contract HY/2009/15 and relevant reporting has been
ceased in the reporting month.
Table I Summary of
Water Quality Monitoring Exceedances in Reporting Month
Water
quality monitoring Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
||||||||
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
||
C1 |
0 |
0 |
2 |
3 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
|
HK/2012/08 |
WSD19 |
0 |
0 |
3 |
5 |
0 |
1 |
0 |
0 |
2 |
2 |
0 |
2 |
P1 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
|
P3 |
0 |
0 |
1 |
1 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
|
P4 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
P5 |
0 |
0 |
3 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/02 |
RW21-P789 |
0 |
0 |
1 |
3 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
HY/2010/08 |
C7 |
0 |
0 |
0 |
2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Total |
0 |
0 |
11 |
16 |
1 |
1 |
0 |
0 |
6 |
2 |
0 |
2 |
- 4-week post construction water quality monitoring at WSD9, WSD10, WSD15 and WSD17 were completed on 6 Feb 2012 and the water quality monitoring at WSD 10 and WSD15 were temporary suspended since 8 Feb 2012, and WSD9 and WSD17 was implemented with respect to HK/2009/02 from 8 Feb 2012 onwards.
- C8 and C9 were implemented with
respect to HY/2009/19 from 28 Jan 2012.
- C8 & C9 were temporary
suspended since 4 March 2013.
- WSD7 and WSD20 water quality
monitoring were temporarily suspended from 27 Apr 2012.
- C2, C3 C4e and C4w water quality monitoring
station was temporarily suspended since 22 Apr 2013
- P1, P3, P4 and P5 were commenced since 24
Apr 2013
- C5e and C5w water quality
monitoring station was temporarily suspended since 29 Jul 2013.
- WSD21 water quality monitoring
station was temporarily suspended since 12 Mar 2014
- WSD9 and WSD17 water quality
monitoring station was temporarily suspended since 8 Sep 2014 flood tide.
- The water
quality monitoring station C1 shall be associated with Contract No. HK/2009/02
upon commencement of marine works under DP3 at WCR3 area.
- The water quality monitoring
station RW21-P789 was adjusted to RW21-P789E and RW21-P789W since 28 November
2016 ebb-tide.
- The water
quality monitoring was reverted to previous monitoring station RW21-P789 from
PW21-P789E and RW21-P789W from 25 January 2017 onwards.
xxv.
17 action level and 18 limit level of Turbidity exceedances and 1 action
level and 3 limit level of Suspended Solid exceedances were recorded in this reporting
month.
xxvi.
After investigation, it is considered that the 17 action level and 18
limit level of Turbidity exceedances and 1 action level and 3 limit level of
Suspended Solid exceedances recorded in this reporting month were not related
to Project works.
xxvii.
The details of the recorded exceedance can be referred to Section
6.4.
xxviii.
Enhanced
DO monitoring at 3 monitoring stations in Causeway Bay Typhoon Shelter and
Ex-Public Cargo Works Area was conducted three days per week during the
reporting period. The action and limit level exceedances of water quality
monitoring are summarized in Table II.
Table II Summary of Enhanced
Dissolved Oxygen Monitoring Exceedances in Reporting Month
|
|
Water quality monitoring Station |
Mid-flood |
Mid-ebb |
||
|
Contract no. |
DO |
DO |
|||
|
|
AL |
LL |
AL |
LL |
|
|
C6 |
0 |
0 |
0 |
0 |
|
|
Total |
0 |
0 |
0 |
0 |
|
Remarks:
1. Enhanced DO monitoring at Windsor House Cooling (Station Ref: C7) was temporarily suspended since 22 October 2014 with respect to the formation of temporary reclamation zone TS3 and to be resumed upon removal of the respective temporary reclamation zone.
2.
Enhanced
DO monitoring at Monitoring station Ex-WPCWA SE was temporarily suspended from
31 August 2015 with respect to seawall reinstatement works and formation of
active works area. The Enhance DO monitoring at Ex-WPCWA SE was resumed on 11
May 2016 due to completed section of seawall reinstatement works at Ex-PCWA.
xxix.
No action or limit level exceedance for enhanced dissolved oxygen
monitoring recorded in this reporting month.
Complaints, Notifications of Summons and Successful
Prosecutions
xxx.
No environmental complaint received in this reporting month.
Site Inspections and Audit
xxxi.
The
Environmental Team (ET) conducted weekly site inspections for Contract nos.
HK/2009/01, HK/2009/02, HY/2009/15, HY/2009/19, HK/2012/08 and HY/2010/08 under
EP no. EP-356/2009 in the reporting month. Major observations and
recommendations made during the audit sessions were rectified by the
Contractors. No non-conformance was identified during the site inspections.
Future Key Issues
xxxii.
In
coming reporting month, the principal work activities of individual contracts are
anticipated as follows:
Contract no. HK/2009/01 – Wan Chai Development
Phase II – Central –Wanchai Bypass at HKCEC
Nil
Contract
no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at
Wan Chai East
·
Nil
Contract
no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter
Section)
·
Nil
Contract
no. HY/2009/19- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern
Corridor Link
Nil
Contract
no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at
Wan Chai West
·
Construction of Box 1 unit and backfilling
Contract no.
HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip Road 8)
·
Diversion pipe maintenance
·
Diaphragm Wall Removal Works
·
Removal of reclamation at TS3E and TS3W
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to work as the
Environmental Team (ET) under Environmental Permit no. EP-356/2009 and Further
Environmental permit nos. FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009, FEP-06/356/2009,
FEP-07/356/2009 and FEP-08/356/2009 to implement the Environmental Monitoring
and Audit (EM&A) programme as stipulated in the EM&A Manual of the
approved Environmental Impact Assessment (EIA) Report for Wan Chai Development
phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the
EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and
Island Eastern Corridor Link (Register No. AEIAR-041/2001).
1.1.2.
This report presents the environmental monitoring and auditing work carried
out in accordance to the Section 10.3 of EM&A Manual and “Environmental
Monitoring and Audit Requirements” under Particular Specification Section
27.
1.1.3.
This report documents the finding of EM&A works for Environmental
Permit no. EP-356/2009, Further Environmental Permit no. FEP-02/356/2009,
FEP-03/356/2009, FEP-04/356/2009, FEP-06/356/2009, FEP-07/356/2009 and
FEP-08/356/2009 during the period of 27 October
2017 to 26 November 2017. The cut-off date of reporting is at 26th of each reporting
month.
Section 1 Introduction – details the scope and structure of the report.
Section 2 Project
Background – summarizes background and
scope of the project, site description, project
organization and contact details of key personnel during the reporting period.
Section 3 Status of Regulatory Compliance – summarizes the status of valid Environmental Permits /
Licenses during the reporting period.
Section 4 Monitoring
Requirements – summarizes all monitoring
parameters, monitoring methodology and equipment, monitoring locations,
monitoring frequency, criteria and respective event and action plan and
monitoring programmes.
Section 5 Monitoring
Results – summarizes the monitoring
results obtained in the reporting period.
Section 6 Compliance Audit – summarizes
the auditing of monitoring results, all exceedances environmental
parameters.
Section 7 Cumulative Construction Impact due
to the Concurrent Projects – summarizes the relevant cumulative
construction impact due to the concurrent activities of the concurrent Projects.
Section 8 Environmental Site Audit – summarizes the findings of weekly site inspections
undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.
Section 9 Complaints, Notification of
summons and Prosecution – summarizes the cumulative statistics on
complaints, notification of summons and prosecution
Section 10 Conclusion
2.1.1.
“Wan Chai Development phase II and Central-Wan Chai Bypass” and
“Central-Wan Chai Bypass and Island Eastern Corridor Link” (hereafter called
“the Project”) are Designed Project (DP) under the Environmental Impact
Assessment Ordinance (Cap. 499) (EIAO). The Environmental Impact Assessment
(EIA) Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link
(Register No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan
Chai Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001
and 11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development Phase II (WDII) is to provide
land at Wan Chai North and North Point for construction of the Central-Wan Chai
Bypass and Island Eastern Corridor Link (CWB). Land formed under the project
will be developed as a world-class waterfront promenade joining that at the new
Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB to provide relief to
the very congested east-west Connaught Road Central/Harcourt Road / Gloucester
Road Corridor (the Corridor) which is currently operating beyond its capacity.
The CWB will provide relief to the existing congestion along the Corridor and
cater for the anticipated growth of traffic on Hong Kong Island. Without the
CWB and its access roads, there will not be sufficient capacity to serve the
heavy traffic demands at both strategic and local levels.
2.2.1.
The Project is located mainly in Wan Chai North, Causeway Bay and North
Point, and is demarcated by Gloucester Road and Victoria Park Road to the
south, Fenwick Pier Street to the west and Tong Shui Road Interchange to the
east, as shown in Figure
2.1.
2.2.2.
The study area encompasses existing developments along the Wan Chai,
Causeway Bay and North Point shorelines. Major land uses include the Hong Kong
Convention & Exhibition Centre (HKCEC) Extension, the Wan Chai Ferry Pier,
the ex-Wan Chai Public Cargo Working Area (ex-PCWA), the Royal Hong Kong Yacht
Club (RHKYC), the Police Officers’ Club, the Causeway Bay Typhoon Shelter
(CBTS) and commercial and residential developments.
2.2.3.
The scope of the Project
comprises:
·
Land
formation for key transport infrastructure and facilities, including the Trunk
Road (i.e.
CWB) and the associated slip roads for connection to the Trunk Road and for through
traffic from Central to Wan Chai and Causeway Bay. The land formed for the above
transport infrastructure will provide opportunities for the development of an
attractive waterfront promenade for the enjoyment of the public
·
Reprovisioning
/ protection of the existing facilities and structures affected by the land
formation works mentioned above
·
Extension,
modification, reprovisioning or protection of existing storm water drainage
outfalls, sewerage outfalls and watermains affected by the revised land use and
land formation works mentioned above
·
Upgrading
of hinterland storm water drainage system and sewerage system, which would be
rendered insufficient by the land formation works mentioned above
·
Provision
of the ground level roads, flyovers, footbridges, necessary transport
facilities and the associated utility services
·
Construction
of the new waterfront promenade, landscape works and the associated utility
services
·
The
Trunk Road (i.e. CWB) within the study area and the associated slip roads for
connection to the Trunk Road.
2.2.4.
The project also contains various Schedule 2 DPs that, under the EIAO,
require Environmental Permits (Eps) to be granted by the DEP before they may be
either constructed or operated. Table 2.1 summarises the five
individual DPs under this Project. Figure 2.1 shows the locations of these
Schedule 2 DPs.
Table 2.1 Schedule
2 Designated Projects under this Project
Item |
Designated
Project |
EIAO
Reference |
Reason for
inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project, there are a number of
contracts sub-dividing the whole works area into different work areas to be
commenced. Contractors of individual contracts will be required by the EP
holder to apply Further Environmental Permits (FEP) such that the impact
monitoring stations are sub-divided accordingly to facilitate the
implementation of EM&A programme and to streamline the EM&A reporting
for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are summarized in Table 2.2.
Table 2.2 Details
of Individual Contracts under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HK/2009/01 |
Wan Chai Development Phase II – Central –Wanchai Bypass at Hong Kong
Convention and Exhibition Centre |
DP3, DP6 |
23 July 2010 |
DP1, DP2 |
25 August 2011 (Completed) |
||
HK/2009/02 |
Wan Chai Development Phase II – Central – Wan Chai Bypass at WanChai
East |
DP3, DP5 |
5 July 2010 |
DP1 |
26 April 2011 |
||
HY/2009/11 |
Wan Chai Development Phase II and Central – Wan Chai Bypass – North
Point Reclamation |
DP3 |
17 March 2010 (Completed) |
HY/2009/15 |
Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) |
DP3 |
10 November 2010 |
DP1 |
13 July 2011 (Completed) |
||
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 (Completed) |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street |
DP1 |
September 2010 (Completed) |
HY/2009/17 |
Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced
piling works. |
DP1 |
5 October 2010 (Completed) |
HY/2009/18 |
Central – Wan Chai Bypass (CWB) – Central Interchange |
DP1 |
21 April 2011 |
HY/2009/19 |
Central – Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2012/08 |
Wan Chai
Development Phase II Central- Wan Chai Bypass at
Wan Chai West |
DP1,DP2,
DP3 |
10 March 2014 |
HY/2010/08 |
Central- Wanchai Bypass Tunnel – Tunnel (Slip Road 8) |
DP1, DP2, DP3 |
21 March 2013 |
HY/2011/08 |
Central-Wan Chai Bypass (CWB) – Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning |
DP1 |
8 October 2014 |
2.4.1.
Civil Engineering and Development Department and Highways Department are
the overall project controllers for the Wan Chai Development Phase II and Central-Wan
Chai Bypass respectively. For the construction phase of the Project, Project
Engineer, Contractor(s), Environmental Team and Independent Environmental
Checker are appointed to manage and control environmental issues.
2.4.2.
The proposed project organization and lines of communication with
respect to environmental protection works are shown in Figure
2.2. Key personnel and contact
particulars are summarized in Table 2.3:
Table 2.3 Contact Details of Key
Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineer’s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer’s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3912 3388 |
3912 3328 |
|
Chun Wo – Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Project
Manager |
Mr. Simon Liu |
9304 8355 |
2587 1878 |
Site Agent |
Mr. Andy Yu |
9648 4896 |
|||
Environmental
Officer |
Mr. Terry
Tsang |
6683 9394 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project
Manager |
Mr. Paul Yu |
3658-3085 |
2827 9996 |
Quality & Environmental Manager |
Mr. C.P. Ho |
9191 8856 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Director |
Chris Leung |
3557 6393 |
2566 2192 |
Senior Site Manager |
Y Huo |
3557 6368 |
|||
Contractor’s Representative |
Rex Lau |
3557 6405 |
|||
Environmental Officer |
Andy Mak |
3557 6347 |
|
||
Chun Wo – CRGL – MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Rayland Lee |
3758 6788 |
3757 8901 |
Site Agent |
David Lau |
3758 8879 |
|||
Deputy Site Agent |
Andy Chan |
9879 4325 |
|||
Environmental Manager / Environmental Officer |
M.H. Isa |
9884 0810 |
|||
|
|
Construction Manager (Marine) |
Wingo Wong |
9300 2625 |
|
Construction Manager (Land) |
Ivan Wong |
9200 7552 |
|||
China State- Build King Joint Venture |
Contractor under Contract no. HK/2012/08 |
Project Director |
C. N. Lai |
9106 5806 |
2877 1522 |
Project Manager |
Eddie Chung |
9189 8118 |
|||
Site Agent |
Keith Tse |
9037 1839 |
|||
Environmental Officer |
James Ma |
9130 9549 |
|||
China State |
Contractor under
Contract no. HY/2010/08 |
Project Director |
Chris Leung |
3467 4299 |
2566 8061 |
|
|
Project Manager |
Chan Ying Lun |
3418 3001 |
|
|
|
Site Agent |
Thomas Lui |
3557 6452 |
|
|
|
Environmental Officer |
Gabriel Wong |
35576466 |
|
Ramboll Environ Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam
Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
In the reporting month, the principal work activities of individual
contracts conducted are as follow:
Contract no. HK/2009/01 – Wan Chai Development
Phase II – Central –Wanchai Bypass at HKCEC
Nil
Contract no. HK/2009/02 – Wan Chai Development
Phase II – Central – Wan Chai Bypass at Wan Chai East
·
Nil
Contract no. HY/2009/15 – Central-Wanchai Bypass –
Tunnel (Causeway Bay Typhoon Shelter Section)
·
Nil
Contract no. HY/2009/19- Wan Chai Bypass Tunnel
(North Point Section) and Island Eastern Corridor Link
Nil
Contract no. HK/2012/08 – Wan Chai Development
Phase II – Central- Wan Chai Bypass at Wan Chai West
Construction of Box 1 unit and backfilling
Trimming of rock level
Contract no. HY/2010/08 –Central - Wan Chai Bypass
(CWB) –Tunnel (Slip Road 8)
Diversion pipe maintenance
Diaphragm wall removal works
Removal of reclamation at TS3E and TS3W
2.4.4.
In coming reporting month, the principal work activities of individual
contracts are anticipated as follows:
Contract no. HK/2009/01 – Wan Chai Development
Phase II – Central –Wanchai Bypass at HKCEC
Nil
Contract no. HK/2009/02 – Wan Chai Development
Phase II – Central – Wan Chai Bypass at Wan Chai East
·
Nil
Contract no. HY/2009/15 – Central-Wanchai Bypass –
Tunnel (Causeway Bay Typhoon Shelter Section)
·
Nil
Contract no. HY/2009/19- Wan Chai Bypass Tunnel
(North Point Section) and Island Eastern Corridor Link
Nil
Contract no. HK/2012/08 – Wan Chai Development
Phase II – Central- Wan Chai Bypass at Wan Chai West
·
Construction of Box 1 unit and backfilling
Contract no. HY/2010/08 –Central - Wan Chai Bypass
(CWB) –Tunnel (Slip Road 8)
·
Diversion pipe maintenance
·
Diaphragm Wall Removal Works
·
Removal of reclamation at TS3E and TS3W
3.1.1.
A summary of the current status on licences and/or permits on
environmental protection pertinent to the Project is shown in Table 3.1.
Table 3.1 Summary of
the current status on licences and/or permits on environmental protection
pertinent to the Project
Permits and/or
Licences |
Reference No. |
Issued Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Superseded |
Environmental Permit |
EP-364/2009/B |
20 Sep 2012 |
Superseded |
Environmental Permit |
EP-364/2009/C |
11 Jul 2014 |
Superseded |
Environmental Permit |
EP-364/2009/D |
24 Nov 2016 |
Superseded |
Environmental Permit |
EP-364/2009/E |
22 Dec 2016 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental
Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Surrendered |
Further Environmental
Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental
Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-04/356/2009 |
22 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-05/356/2009 |
24 Mar 2011 |
Surrendered |
Further Environmental Permit |
FEP-01/364/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-02/364/2009 |
21 Apr 2010 |
Valid |
Further Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
Surrendered |
Further Environmental Permit |
FEP-04/364/2009/A |
14 Oct 2010 |
Surrendered |
Further Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-06/364/2009/A |
22 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-07/364/2009/B |
20 Sep 2012 |
Surrendered |
Further Environmental Permit |
FEP-07/364/2009/D |
24 Nov 2015 |
Valid |
Further Environmental Permit |
FEP-08/364/2009/A |
15 Jun 2012 |
Surrendered |
Further Environmental Permit |
FEP-06/356/2009 |
5 Mar 2013 |
Valid |
Further Environmental Permit |
FEP-07/356/2009 |
26 July 2013 |
Valid |
Further Environmental Permit |
FEP-09/364/2009/B |
5 March 2013 |
Valid |
Further Environmental Permit |
FEP-10/364/2009/B |
26 July 2013 |
Valid |
Further Environmental Permit |
FEP-11/364/2009/B |
2 May 2014 |
Superseded |
Further Environmental Permit |
FEP-08/356/2009 |
1 Aug 2016 |
Valid |
Further Environmental Permit |
FEP-11/364/2009/E |
22 Dec 2016 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project, the status of permits
and/or licences under the individual contract(s) are presented as below:
Contract no. HK/2009/01 – Wan Chai
Development Phase II – Central –Wanchai Bypass at HKCEC
3.1.3.
Summary of the current status on licences and/or permits on
environmental protection pertinent and submission for contract no. HK/2009/01
under FEP-02/356/2009 are shown in Table 3.2 and Table 3.3.
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
313088 |
06 Jan 2010 |
N/A |
Valid |
Discharge Licence |
WT00024952-2016 |
6 Jul 2016 |
31 Jul 2021 |
Valid |
WT00024844-2016 |
29 Jun 2016 |
31 Mar 2020 |
Valid |
|
Billing account under Waste Disposal
Ordinance |
7010069 |
21
Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21
Jan 2010 |
N/A |
Valid |
Table 3.3 Summary
of submission status under FEP-02/356/2009 Condition
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main Construction Companies |
13 Apr 2010 |
Condition 2.7 |
Works Schedule and
Location Plan |
8 Apr 2010 |
Condition 2.8 |
Silt Curtain
Deployment Plan (Rev. 5) |
24 Aug 2012 |
Silt Curtain
Deployment Plan (Rev. 4) |
12 July 2012 |
|
Silt Curtain
Deployment Plan (Rev. 3) |
27 June 2012 |
|
Silt Curtain
Deployment Plan |
19 Apr 2010 |
|
Condition 2.9 |
Silt Screen
Deployment Plan (Rev. 9) |
5 Nov 2015 |
Silt Screen
Deployment Plan (Rev. 8) |
7 Sep 2015 |
|
Silt Screen
Deployment Plan (Rev. 7) |
21 Nov 2014 |
|
Silt Screen
Deployment Plan (Rev. 6) |
20 Aug 2014 |
|
Silt Screen
Deployment Plan (Rev.5) |
24 Jul 2013 |
|
Silt Screen
Deployment Plan (Rev.4) |
15 Nov 2012 |
|
Silt Screen
Deployment Plan |
19 Apr 2010 |
|
Conditions 2.8 and
2.9 |
Supplementary
Document on Silt Curtain and Silt Screen Deployment Plan |
19 Jul 2010 |
Report on Field
Testing for Silt Curtain |
26 Aug 2010 |
|
Report on Field
Testing for Silt Curtain (Rev. A) |
15 Nov 2010 |
|
Condition 2.12(d) |
Alternative
Proposal on Concurrent Dredging for Sewage Pipeline and Cross Harbour Water
Mains |
15 Apr 2011 |
Condition 2.17 |
Noise Management
Plan |
23 Apr 2010 |
Condition 2.18 |
Landscape Plan
(Erection of Decorative Screen Hoarding along Construction Site around Hong
Kong Exhibition and Convention Centre) |
15 May 2010 |
|
Landscape Plan
(Night-time Lighting) |
22 Oct 2010 |
|
Landscape Plan
(Rev. B) |
15 Nov 2010 |
Condition 1.12 |
Notification of
Commencement Date |
20 Jun 2011 |
Condition 2.6 to
2.8 |
Management
Organization, Works Schedule and Location Plan |
18 May 2011 |
Condition 2.9 |
Silt Screen
Deployment Plan |
10 Jun 2011 |
Condition 2.18 |
Landscape Plan |
31 Oct 2013 |
Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at WanChai East
3.1.4.
Summary of
the current status on licences and/or permits on environmental protection
pertinent and submission for contract no. HK/2009/02 under FEP-03/356/2009 are
shown in Table 3.4 and Table 3.5.
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
|
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS0726-17 |
22 Aug 2017 |
03 Sep 2017 to 25 Feb 2018 |
Superseded |
GW-RS0751-17 |
4 Sep 2017 |
10 Sep 2017 to 04 Feb 2018 |
Superseded |
|
GW-RS0756-17 |
4 Sep 2017 |
07 Sep 2017 to 28 Feb 2018 |
Valid |
|
GW-RS0763-17 |
4 Sep 2017 |
06 Sep 2017 to 04 Mar 2018 |
Superseded |
|
GW-RS0843-17 |
28 Sep 2017 |
07 Oct 2017 to 25 Mar 2018 |
Valid |
|
GW-RS0869-17 |
10 Oct 2017 |
15 Oct 2017 to 11 Mar 2018 |
Valid |
|
GW-RS0884-17 |
12 Oct 2017 |
24 Oct 2017 to 23 Apr 2018 |
Valid |
|
GW-RS0885-17 |
12 Oct 2017 |
14 Oct 2017 to 12 Apr 2018 |
Valid |
|
Discharge Licence |
WT00022295-2015 |
12 Aug 2015 |
31 July 2020 |
Valid |
|
WT00025276-2016 |
19 Sep 2016 |
31 July 2021 |
Valid |
Billing Account under Waste Disposal Ordinance (Land) |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Billing Account under Waste Disposal Ordinance (Marine) |
7011496 |
6 Oct 2010 |
N/A |
Valid |
Registration as Chemical Waste Producer (Wan Chai) |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Registration as Chemical Waste Producer (TKO 137) |
WPN5213-839-C3593-02 |
22 Sep 2010 |
N/A |
Valid |
Marine Dumping Permit (Dredged Sediment Requiring Type 1 – Open Sea
Disposal) |
EP/MD/17-191 |
16 May 2017 |
18 May 2017 to 17 Nov 2017 |
Valid |
Table
3.5 Summary of submission
status under FEP-03/356/2009 Condition
EP Condition |
Submission |
Date of Submission |
Condition 1.12 |
Commencement Date
of Construction of Marine Works |
8 April 2010 |
Condition 2.6 |
Management
Organization of Main Construction Companies |
10 April 2010 |
Condition 2.7 |
Works Schedule and
Location Plans |
8 April 2010 |
Condition 2.8 |
Silt Curtain
Deployment Plan (Revision A) |
20 April 2010 |
Silt Curtain
Deployment Plan (Revision B) |
25 May 2010 |
|
Silt Curtain
Deployment Plan (Revision C) |
14 Jun 2010 |
|
Silt Curtain
Deployment Plan (Revision H) |
15 Feb 2011 |
|
Silt Curtain
Deployment Plan (Revision I) |
17 Nov 2011 |
|
Silt Curtain
Deployment Plan (Revision J) |
15 Feb 2012 |
|
Silt Curtain
Deployment Plan (Revision K) |
3 May 2012 |
|
Silt Curtain
Deployment Plan (Revision L) |
25 Oct 2012 |
|
Silt Curtain
Deployment Plan (Revision M) |
30 Nov 2012 |
|
Condition 2.9 |
Silt Screen
Deployment Plan |
21 April 2010 |
Supplementary
Information for Existing WSD Salt Water Intakes at Quarry Bay and Sai Wan Ho |
5 Oct 2010 |
|
Silt Screen
Deployment Plan (Revision B) |
15 Feb 2012 |
|
Silt Screen
Deployment Plan (Revision C) |
3 May 2012 |
|
Silt Screen
Deployment Plan (Revision D) |
10 Dec 2012 |
|
|
Silt Screen
Deployment Plan (Revision E) |
6 May 2013 |
|
Silt Screen
Deployment Plan (Revision F) |
23 Nov 2016 |
Condition 2.17 |
Noise Management
Plan |
6 May 2010 |
Condition 2.18 |
Landscape Plan
(Decorative Screen Hoarding) |
11 May 2010 |
Landscape Plan
(Control of Night Time Lighting) |
2 June 2010 |
|
Landscape Plan
(Combined Version) |
20 July 2011 |
|
Landscape Plan
(Combined Version) |
5 Aug 2011 |
|
----- |
Acknowledge of
Submission |
22 Aug 2011 |
Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay
Typhoon Shelter Section)
3.1.5.
Summary of the current status on licences and/or permits on
environmental protection pertinent and submission for contract no. HY/2009/15
under FEP-04/356/2009 are shown in Table 3.6 and Table 3.7.
Table 3.6 Cumulative Summary of
Valid Licences and Permits under Contract no. HY/2009/15
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental Permit |
FEP-04/356/2009 |
22 Nov 2010 |
N/A |
Valid |
Notification of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Registration as a
Chemical Waste Producer |
WPN5213-147-C1169-35 |
15 Nov 2010 |
N/A |
Valid |
Billing Account under Waste Disposal
Ordinance |
7011553 |
30 Sep 2010 |
N/A |
Valid |
Table 3.7 Summary
of submission status under FEP-04/356/2009 Condition
FEP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main Construction
Companies |
30 Sep 2010 |
Amendment for Management Organization of Main
Construction Companies |
16 May 2011 |
|
Condition 2.7 |
Works Schedule and Location Plans |
27 Oct 2010 |
|
Amendment for Works Schedule and Location
Plans |
12 Nov 2010 |
Condition 2.8 |
Silt Curtain Deployment Plan |
30 Nov 2010 |
|
Amendment for Silt Curtain Deployment Plan |
24 Feb 2011 |
Amendment for Silt Curtain Deployment Plan |
11 May 2011 |
|
Amendment for Silt Curtain Deployment Plan |
11 Sep 2012 |
|
Amendment for Silt Curtain Deployment Plan |
30 Oct 2012 |
|
Condition 2.9 |
Silt Screen
Deployment Plan |
19 Oct 2010 |
Amendment for Silt Screen Deployment Plan |
18 Feb 2011 |
|
Amendment for Silt Screen Deployment Plan |
15 Jun 2011 |
|
Condition 2.18 |
Proposal
for the Removal of Odorous Sediment and Slime |
13 Jan 2011 |
Amendment for Proposal for the Removal of
Odorous Sediment and Slime |
8 Mar 2011 |
|
|
Amendment for Proposal for the Removal of
Odorous Sediment and Slime |
2 Aug 2011 |
Condition 2.21 |
Landscape Plan |
18 Feb 2011 |
Condition 2.23 |
Noise Management Plan |
20 Oct 2010 |
Amendment for Noise Management Plan |
27 Jan 2011 |
Contract no. HY/2009/19 – Central- Wan Chai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link
3.1.6.
Summary of the current status on licences and/or permits on
environmental protection pertinent for contract no. HY/2009/19 is shown in Table
3.8
Table
3.8 Cumulative Summary of
Valid Licences and Permits under Contract no. HY/2009/19
Permit / Licence / Notification / Approval |
Reference No. |
Issued Date |
Valid Period / Expiry date |
Status |
Further Environmental Permit |
FEP-07/364/2009/D |
24 Nov 2015 |
Granted |
Valid |
Notification of Works Under APCO |
326160 |
24 Jan 2011 |
Notified |
Valid |
C&D Waste Disposal |
7012306 |
10 Feb 2011 |
Registered |
- |
Vessel Disposal |
7013285 |
21 July 2011 |
Registered |
- |
Registration as Chemical Waste Producer |
5213-151-C3654-01 |
24 Mar 2011 |
Registered |
- |
Contract no. HK/2012/08 – Wan Chai Development
Phase II – Central- Wan Chai Bypass at Wan Chai West
3.1.7.
Summary of the current status on licences and/or permits on
environmental protection pertinent and submission for contract no. HK/2012/08
under FEP-08/356/2009 are shown in Table 3.9 and Table 3.10.
Table 3.9 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2012/08
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-06/356/2009 |
5 Mar 2013 |
N/A |
Valid |
|
FEP-08/356/2009 |
1 Aug 2016 |
N/A |
Valid |
Notification of Works Under APCO |
355439 |
4 Feb 2013 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
5213-134-C3790-01 |
30 Jun 2016 |
N/A |
Valid |
Billing Account under Waste Disposal Ordinance |
7016883 |
18 Feb 2013 |
N/A |
Valid |
Water Discharge Licence |
WT00020594-2014 |
22 Dec 2014 |
31 Jan 2019 |
Valid |
Construction Noise Permit |
GW-RS0385-17 |
27 Apr 2017 |
5 May 2017 to 04 Nov
2017 |
Superseded |
GW-RS0505-17 |
9 Jun 2017 |
13 Jul 2017 to 12 Jan
2018 |
Valid |
|
GW-RS0593-17 |
11 Jul 2017 |
13 Jul 2017 to 12 Jan
2018 |
Valid |
|
GW-RS0504-17 |
8 Jun 2017 |
12 Jul 2017 to 11 Jan
2018 |
Valid |
|
GW-RS0676-17 |
3 Aug 2017 |
26 Aug 2017 to 25 Feb
2018 |
Valid |
|
GW-RS0914-17 |
23 Oct 2017 |
05 Nov 2017 to 04 Apr
2018 |
Valid |
|
Dumping Permit (Type 1 – Open Sea Disposal) |
EP/MD/18-039 |
8 Aug 2017 |
11 Aug 2017 to 10 Feb
2018 |
Valid |
Table 3.10 Summary of submission
status under EP-356/2009 and FEP-06/356/2009
Condition
FEP Condition |
Submission |
Date of Submission |
Condition 2.8 |
Silt Curtain Deployment Plan (Rev. 3) |
Submitted
on 25 Nov 2013 was returned to CSLJV by EPD. |
Condition 2.9 |
Silt Screen Deployment Plan (Rev. 2) |
Generally
in order as commented by EPD on 19 Sep 2013 |
Condition 2.23 |
Noise Management Plan (Rev. 2) |
Generally in order as commented by EPD on 15 Aug 2013 |
Condition 2.24 |
Landscape Plan (Rev. 3) |
Generally
in order as commented by EPD on 31 Oct 2013 |
Contract no. HY/2010/08 –Central - Wan Chai Bypass
(CWB) –Tunnel (Slip Road 8)
3.1.8.
Summary of the current status on licences and/or permits on
environmental protection pertinent and submission for contract no. HY/2010/08
under FEP-07/356/2009 are shown in Table 3.11 and Table 3.12.
Table 3.11
Cumulative Summary of Valid Licences and Permits under Contract no. HY/2010/08
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-07/356/2009 |
26 Jul 2013 |
NA |
Valid |
|
FEP-10/364/2009/B |
26 Jul 2013 |
NA |
Valid |
Notification of Works Under APCO |
357176 |
2 Apr 2013 |
NIL |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-147-C1169-44 |
27 Mar 2013 |
NIL |
Valid |
Billing Account under Waste Disposal Ordinance |
7017170 |
27 Mar 2013 |
NIL |
Valid |
Billing
Account under Waste Disposal Ordinance (Dumping by Vessel) |
7020947 |
22 Dec 2014 |
NIL |
Valid. |
Water Discharge Licence |
WT00020468-2014 |
3 Dec 2014 |
9 Jul 2013 to 31 Jul 2018 |
Valid |
WT00028744-2017 |
4 Aug 2017 |
4 Aug 2017 to 31 Aug 2019 |
Valid |
|
Construction Noise Permit |
GW-RS0877-17 |
10 Oct 2017 |
18 Oct 2017
to 17 Apr 2017 |
Valid |
Table
3.12 Summary of submission
status under EP-356/2009 and FEP-07/356/2009
Condition
FEP Condition |
Submission |
Date of Submission |
Condition 2.8 |
Silt Curtain Deployment Plan (rev03) |
24
Dec 2014 |
Condition 2.9 |
Silt Curtain Deployment Plan (rev03) |
29 Sept 2017 |
Condition 2.9 |
Silt Screen Deployment Plan (rev02) |
18 Feb
2015 |
Condition 2.23 |
Noise Management Plan (rev02) |
25 Mar 2014 |
Condition 2.24 |
Landscape Plant (rev04) |
23 Sep 2014 |
Noise Monitoring Stations
4.1.1.
The noise monitoring stations for the Project are listed and shown in Table
4.1 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.1 Noise
Monitoring Station
Station |
Description |
M1a |
Footbridge for Ex-Harbour Road Sports Centre* |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire
Station |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist Church
Henrietta Secondary School |
Remarks*: With respect to the demolition of Ex-Harbour Road Sports
Centre, the respective noise monitoring station M1a – Harbour Road Sports
Centre were finely adjusted on 16 and 25 May 2017 and thereafter to the
Footbridge for Harbour Road Sports for noise monitoring
Noise Monitoring
Parameters, Frequency and Duration
4.1.2.
The construction noise level shall
be measured in terms of the A-weighted equivalent continuous sound pressure
level (Leq). Leq (30 minutes) shall be used as the monitoring
parameter for the time period between 0700 and 1900 hours on normal weekdays.
For all other time periods, Leq (5 minutes) shall be employed for
comparison with the Noise Control Ordinance (NCO) criteria. Supplementary information for
data auditing, statistical results such as L10 and L90 shall also be obtained
for reference.
4.1.3.
Noise monitoring shall be carried out at all the designated monitoring
stations. The monitoring frequency shall depend on the scale of the
construction activities. The following is an initial guide on the regular
monitoring frequency for each station on a weekly basis when noise generating
activities are underway:
·
One
set of measurements between 0700 and 1900 hours on normal weekdays.
4.1.4.
If construction works are extended to include works during the hours of
1900 – 0700 as well as public holidays and Sundays, additional weekly impact
monitoring shall be carried out during respective restricted hours
periods. Applicable permits under NCO shall be obtained by the Contractor.
Monitoring Equipment
4.1.5.
As referred to in the Technical Memorandum ™ issued under the NCO, sound
level meters in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be
used for carrying out the noise monitoring. Immediately prior to and following
each noise measurement the accuracy of the sound level meter shall be checked
using an acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agree to within 1.0 dB.
4.1.6.
Noise measurements shall not be made in fog, rain, wind with a steady
speed exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall
be checked with a portable wind speed meter capable of measuring the wind speed
in m/s.
Air Quality Monitoring
Stations
4.2.1.
The air monitoring stations for the Project are listed and shown in Table
4.2 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table
4.2 Air Monitoring Station
Station ID |
Monitoring
Location |
Description |
CMA1b |
Harbour Grand Hotel
Boundary Wall** |
North Point |
CMA2a |
Causeway Bay Community
Centre |
Causeway Bay |
CMA3a |
CWB PRE Site Office * |
Causeway Bay |
CMA4a |
Society for the
Prevention of Cruelty to Animals |
Wan Chai |
CMA5b |
Pedestrian Plaza*** |
Wan Chai |
CMA6a |
WDII PRE Site Office * |
Wan Chai |
Remarks*: As per the ENPC meeting in
March 2011, the monitoring stations CMA3a – Future CWB site office at Wanchai
Waterfront Promenade was renamed as remark.
Remarks**: The location ID of monitoring
station CMA1b was updated as “Harbour Grand Hotel Boundary Wall” from 05 June
2017 onwards.
Remarks***: The station ID and
monitoring location was updated in December 2014 with respect to monitoring
station relocation.
Air Monitoring Parameters,
Frequency and Duration
4.2.2.
One-hour and 24-hour TSP levels should be measured to indicate the
impacts of construction dust on air quality. The 24-hour TSP levels shall be
measured by following the standard high volume sampling method as set out in
the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.
4.2.3.
All relevant data including temperature, pressure, weather conditions,
elapsed-time meter reading for the start and stop of the sampler,
identification and weight of the filter paper, and any other local atmospheric
factors affecting or affected by site conditions, etc., shall be recorded down
in detail.
4.2.4.
For regular impact monitoring, the sampling frequency of at least once
in every six-days, shall be strictly observed at all the monitoring stations
for 24-hour TSP monitoring. For 1-hour TSP monitoring, the sampling frequency
of at least three times in every six-days should be undertaken when the highest
dust impact occurs.
Sampling Procedure and
Monitoring Equipment
4.2.5.
High volume samplers (HVSs) in compliance with the following
specifications shall be used for carrying out the 1-hour and 24-hour TSP
monitoring:
·
0.6
– 1.7 m3 per minute adjustable flow range;
·
equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours operation;
·
installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
·
capable
of providing a minimum exposed area of 406 cm2;
·
flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
·
equipped
with a shelter to protect the filter and sampler;
·
incorporated
with an electronic mass flow rate controller or other equivalent devices;
·
equipped
with a flow recorder for continuous monitoring;
·
provided
with a peaked roof inlet;
·
incorporated
with a manometer;
·
able
to hold and seal the filter paper to the sampler housing at horizontal
position;
·
easily
changeable filter; and
·
capable of operating continuously for a 24-hour period.
4.2.6.
Initial calibration of dust monitoring equipment shall be conducted upon
installation and thereafter at bi-monthly intervals. The transfer standard
shall be traceable to the internationally recognized primary standard and be
calibrated annually. The concern parties such as IEC shall properly document
the calibration data for future reference. All the data should be converted
into standard temperature and pressure condition.
Laboratory Measurement /
Analysis
4.2.7.
A clean laboratory with constant temperature and humidity control, and
equipped with necessary measuring and conditioning instruments to handle the
dust samples collected, shall be available for sample analysis, and equipment
calibration and maintenance. The laboratory should be HOKLAS accredited.
4.2.8.
An alternative non-HOKLAS accredited
laboratory was set-up for carrying out the laboratory analysis,
the laboratory equipment was approved by the ER on
8 February 2011 and
the measurement procedures were witnessed by the IEC. Any measurement
performed by the laboratory was be demonstrated to the satisfaction of
the ER and IEC. IEC shall regularly audit to the measurement performed by the
laboratory to ensure the accuracy of measurement results.
4.2.9.
Filter paper of size 8” x 10” shall be labelled before sampling. It
shall be a clean filter paper with no pinholes, and shall be conditioned in a
humidity-controlled chamber for over 24-hours and be pre-weighed before use for
the sampling.
4.2.10.
After sampling, the filter paper loaded with dust shall be kept in a
clean and tightly sealed plastic bag. The filter paper shall then be returned
to the laboratory for reconditioning in the humidity controlled chamber
followed by accurate weighing by an electronic balance with readout down to 0.1
mg. The balance shall be regularly calibrated against a traceable standard.
4.2.11.
All the collected samples shall be kept in a good condition for 6 months
before disposal.
impact monitoring for
odour patrol
4.2.12.
Odour patrols along the shorelines of Causeway Bay Typhoon Shelter and
ex-Wan Chai Public Cargo Working Area when there is temporary reclamation in
Causeway Bay Typhoon Shelter and/or in the ex-Wan Chai Public Cargo Working
Area, or when there is dredging of the odorous sediment and slime at the
south-western corner of the Causeway Bay Typhoon Shelter. Odour patrols will be
carried out at bi-weekly intervals during July, August and September by a
qualified person of the ET who shall:
·
be
at least 16 years of age;
·
be
free from any respiratory illnesses; and
·
not
be allowed to smoke, eat, drink (except water) or use chewing gum or sweets 30
min
·
before
and during odour patrol
4.2.13.
Odour patrol shall be conducted by independent trained personnel /
competent persons patrolling and sniffing around the shore as shown in Figure 4.1 to detect any
odour at the concerned hours (afternoon is preferred for higher daily
temperature).
4.2.14.
The qualified person will use the nose (olfactory sensor) to sniff
odours at different locations. The main odour emission sources and the areas to
be affected by the odour nuisance will be identified.
4.2.15.
The perceived odour intensity is to be divided into 5 levels which are
ranked in the descending order as follows:
·
0 –
Not detected. No odour perceived or an odour so weak that it cannot be easily characterized
or described;
·
1 –
Slight Identifiable odour, and slight chance to have odour nuisance;
·
2 –
Moderate Identifiable odour, and moderate chance to have odour nuisance;
·
3 –
Strong Identifiable, likely to have odour nuisance;
·
4 –
Extreme Severe odour, and unacceptable odour level.
4.2.16.
The findings including odour intensity, odour nature and possible odour
sources, and also the local wind speed and direction at each location will be
recorded. In addition, some relevant meteorological and tidal data such as
daily average temperature, and daily average humidity, on that surveyed day
will be obtained from the Hong Kong Observatory Station for reference. The
Action and Limit levels for odour patrol are shown in Appendix 4.1.
4.2.17.
The qualified odour patrol member has individual n-butanol thresholds
complied with the requirement of European Standard Method of Air Quality –
Determination of Odour Concentration by Dynamic Olfactometry (EN13725) in the
range of 20 to 80 ppb.
4.3.1.
The EIA Report has identified that the key water quality impact would be
associated with the dredging works during the construction phase. Marine water
quality monitoring for dissolved oxygen (DO), suspended solid (SS) and
turbidity is therefore recommended to be carried out at selected WSD flushing
water intakes. The impact monitoring should be carried out during the proposed
dredging works to ensure the compliance with the water quality standards.
4.3.2.
The updated EM&A Manual for EP-356/2009 (Version in March 2011) is
approval by EPD on 29 April 2011. As such, the Action Level and Limit Level for
the wet season (April – September) will be effected and applied to the water
quality monitoring data from 30 April 2011.
Water Quality Monitoring Stations
4.3.3.
Water quality monitoring was undertaken at 8 monitoring stations for WSD
salt water intakes and cooling water intakes along the seafront of the Victoria
Harbour in the reporting month. The proposed water quality monitoring stations
of the Project are shown in Table 4.3 and Figure 4.1. Appendix 4.1
shows the established Action/Limit Levels for the monitoring works.
Table 4.3 Marine
Water Quality Stations for Water Quality Monitoring
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
Cooling Water Intake |
|||
C1 |
HKCEC Extension |
835885.6 |
816223.0 |
C7 |
Windsor House |
837193.7 |
816150.0 |
P1 |
HKCEC
Phase I |
835774.7 |
816179.4 |
P3 |
The Academy of performing Arts |
835824.6 |
816212.0 |
P4 |
Shui on Centre |
835865.6 |
816220.0 |
P5 |
Government
Buildings (Wanchai
Tower / Revenue Tower / Immigration Tower) |
835895.2 |
816215.2 |
Cooling Water Intake / WSD Salt Water Intake |
|||
RW21-P789 |
Great
Eagle Centre/ Sun Hung Kai Centre/ WSD Wanchai salt water intake / China Resources Building |
836268.0 |
816020.0 |
Remarks: - The cessation of seawater intake operation for C6 was confirmed on 17 May 2011 and the water quality monitoring at C6 was then terminated since 17 May 2011.
- 4-week post construction water quality monitoring at WSD9, WSD10, WSD15 and WSD17 were completed on 6 Feb 2012 and the water quality monitoring at WSD 10 and WSD15 were temporary suspended since 8 Feb 2012, and WSD9 and WSD17 was implemented with respect to HK/2009/02 from 8 Feb 2012 onwards.
- C8 and C9 were implemented with
respect to HY/2009/19 from 28 Jan 2012.
- C8 & C9 were temporary
suspended since 4 March 2013.
- WSD7 and WSD20 water quality
monitoring were temporarily suspended from 27 Apr 2012.
- C2, C3 C4e and C4w water quality monitoring
station was temporarily suspended since 22 Apr 2013
- P1, P3, P4 and P5 were commenced since 24
Apr 2013
- C5e and C5w water quality
monitoring station was temporarily suspended since 29 Jul 2013.
- WSD21 water quality monitoring
station was temporarily suspended since 12 Mar 2014
- WSD9 and WSD17 water quality
monitoring station was temporarily suspended since 8 Sep 2014 flood tide.
- The water quality monitoring station C1 shall be associated with Contract No. HK/2009/02 upon commencement of marine works under DP3 at WCR3 area.
- The
water quality monitoring station RW21-P789 was adjusted to RW21-P789E and RW21-P789W since 28 November
2016 ebb-tide.
- The
water quality monitoring was reverted to previous monitoring station RW21-P789
from PW21-P789E and RW21-P789W from 25 January 2017 onwards.
Water Quality Parameters
4.3.4.
Monitoring of dissolved oxygen (DO), turbidity and suspended solids (SS)
shall be carried out at WSD flushing water intakes and cooling water intakes.
DO and Turbidity are measured in-situ while SS is determined in laboratory.
4.3.5.
In association with the water quality parameters, other relevant data
shall also be measured, such as monitoring location/position, time, sampling
depth, water temperature, pH, salinity, dissolved oxygen (DO) saturation,
weather conditions, sea conditions, tidal stage, and any special phenomena and
work underway at the construction site etc.
Sampling Procedures and
Monitoring Equipment
4.3.6.
The interval between two sets of monitoring should not be less than 36
hours except where there are exceedances of Action and/or Limit Levels, in
which case the monitoring frequency will be increased. Table 4.4
shows the proposed monitoring frequency and water quality parameters. Duplicate
in-situ measurements and water sampling should be carried out in each sampling
event. For selection of tides for in-situ measurement and water sampling, tidal
range of individual flood and ebb tides should be not less than 0.5m.
Table 4.4 Marine
Water Quality Monitoring Frequency and Parameters
Activities |
Monitoring Frequency1 |
Parameters2 |
During the 4-week
baseline monitoring period |
Three days per week,
at mid-flood and mid-ebb tides |
Turbidity, Suspended Solids
(SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
During marine construction works |
Three days per week,
at mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
After completion of marine construction works |
Three days per week,
at mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
Notes:
1.
For selection of tides for in-situ measurement
and water sampling, tidal range of individual flood and ebb tides should be not
less than 0.5m.
2.
Turbidity should be measured in situ whereas SS
should be determined by laboratory.
Dissolved Oxygen and
Temperature Measuring Equipment
4.3.7.
The instrument should be a portable, weatherproof dissolved oxygen
measuring instrument complete with cable, sensor, comprehensive operation
manuals, and use a DC power source. It should be capable of measuring:
·
a
dissolved oxygen level in the range of 0-20 mg/l and 0-200% saturation
·
a
temperature of 0-45 degree Celsius
4.3.8.
It should have a membrane electrode with automatic temperature
compensation complete with a cable. Sufficient stocks of spare electrodes and
cables should be available for replacement where necessary. (e.g.
YSI model 59 meter, YSI 5739 probe, YSI 5795A submersible stirrer with reel and
cable or an approved similar instrument).
4.3.9.
Should salinity compensation not be build-in in the DO equipment,
in-situ salinity shall be measured to calibrate the DO equipment prior to each
DO measurement.
Turbidity Measurement
Instrument
4.3.10.
The instrument should be a portable, weatherproof turbidity-measuring
instrument complete with comprehensive operation manual. The equipment should
use a DC power source. It should have a photoelectric sensor capable of
measuring turbidity between 0‑1000 NTU and be complete with a cable (e.g. Hach
model 2100P or an approved similar instrument).
Sampler
4.3.11.
A water sampler comprises a transparent PVC cylinder, with a capacity of
not less than 2 litres, and can be effectively sealed with latex cups at both
ends. The sampler should have a positive latching system to keep it open and
prevent premature closure until released by a messenger when the sampler is at
the selected water depth (e.g. Kahlsico Water Sampler or an approved similar
instrument).
Sample Container and
Storage
4.3.12.
Water samples for suspended solids measurement should be collected in
high-density polythene bottles, packed in ice (cooled to 4°C without being
frozen), and delivered to ALS Technichem (HK) Pty Ltd. as soon as possible
after collection for analysis.
Water Depth Detector
4.3.13.
A portable, battery-operated echo sounder shall be used for the
determination of water depth at each designated monitoring station. This unit
can either be handheld or affixed to the bottom of the workboat, if the same
vessel is to be used throughout the monitoring programme.
Salinity
4.3.14.
A portable salinometer capable of measuring salinity in the range of
0-40 ppt shall be provided for measuring salinity of the water at each of
monitoring location.
Monitoring Position
Equipment
4.3.15.
A hand-held or boat-fixed type digital Global Positioning System (GPS)
with waypoint bearing indication or other equivalent instrument of similar
accuracy shall be provided and used during monitoring to ensure the monitoring
vessel is at the correct location before taking measurements.
Calibration of In-situ
Instruments
4.3.16.
All in-situ monitoring instrument shall be checked, calibrated and
certified by a laboratory accredited under HOKLAS or equivalent before use, and
subsequently re-calibrated at 3 monthly intervals throughout all stages of the
water quality monitoring. Responses of sensors and electrodes should be checked
with certified standard solutions before each use. Wet bulb calibration for a
DO meter shall be carried out before measurement at each monitoring location.
4.3.17.
For the on site calibration of field equipment by the ET, the BS
127:1993, "Guide to Field and on-site test
methods for the analysis of waters" should be observed.
4.3.18.
Sufficient stocks of spare parts should be maintained for replacements
when necessary. Backup monitoring equipment shall also be made available so
that monitoring can proceed uninterrupted even when some equipment is under
maintenance, calibration, etc.
4.3.19.
Current calibration certificates of equipments are presented in Appendix 4.2.
Laboratory Measurement /
Analysis
4.3.20.
Analysis of suspended solids has been carried out in a HOKLAS accredited
laboratory, ALS Technichem (HK) Pty Ltd. Water samples of about 1L shall be
collected at the monitoring stations for carrying out the laboratory SS
determination. The SS determination work shall start within 24 hours after
collection of the water samples. The SS determination shall follow APHA 19ed or
equivalent methods subject to the approval of IEC and EPD.
Enhanced Water Quality
Monitoring in the ex-Wan Chai Public Cargo
Working Area and the
Causeway Bay Typhoon Shelter
4.3.21.
The enhanced water quality monitoring and audit programme is to avoid
aggravation of odour nuisance from seawater arising from temporary reclamation
in the ex-Wan Chai Public Cargo Working Area and the Causeway Bay Typhoon
Shelter.
4.3.22.
Dissolved oxygen monitoring at the intakes C6 and C7 in Causeway Bay
Typhoon Shelter when there is temporary reclamation in Causeway Bay Typhoon
Shelter and at the south-western and south-eastern corners of the ex-Wan Chai
Public Cargo Working Area. The proposed water quality monitoring stations of
the Project are shown in Table 4.5 and Figure
4.1.
Table 4.5 Marine Water Quality Stations for Enhanced
Water Quality Monitoring
Station |
Location |
C6 |
Excelsior
Hotel |
C7 |
Windsor House |
Ex-WPCWA-SW |
South-western
of the ex-Wan Chai Public Cargo Working Area |
Ex-WPCWA-SE |
South-eastern
of the ex-Wan Chai Public Cargo Working Area |
Remarks:
1. Enhanced DO monitoring at Windsor House Cooling (Station Ref: C7) was temporarily suspended since 22 October 2014 with respect to the formation of temporary reclamation zone TS3 and to be resumed upon removal of the respective temporary reclamation zone.
2.
Enhanced
DO monitoring at Monitoring station Ex-WPCWA SE was temporarily suspended from
31 August 2015 with respect to seawall reinstatement works and formation of
active works area. The Enhance DO monitoring at Ex-WPCWA SE was resumed on 11
May 2016 due to completed section of seawall reinstatement works at Ex-PCWA.
4.3.23.
The monitoring of dissolved oxygen are to be carried out 3 days per
week, at mid-flood and mid-ebb tides for 3 water depths (1m below water
surface, mid-depth and 1m above sea bed, except where the water depth less than
6m, the mid-depth may be omitted. If the water depth be equal to or less than
3m, only the mid-depth will be monitored).
Daily SS Monitoring and 24
hours Turbidity Monitoring System
4.3.24.
During dredging of the sediment at the south-western corner of the
Causeway Bay Typhoon Shelter, daily monitoring of suspended solids and 24
hour monitoring of turbidity at the cooling water intakes (C6 and C7) shall be conducted.
4.3.25.
The 24 hours monitoring of turbidty at the
cooling water intakes (C6 and C7) shall be established
by setting up a continuous water quality monitoring station in front of the
intakes during the dredging activities. The monitoring system include the
turbidity sensor and data logger which is capable of data capturing at every 5 minutes. The data sahll be downloaded daily and compared with the
Action and Limit level determined during the baseline water qualtiy monitoring
at the cooling water intake locations.
Additional Dissovled
oxygen Monitoring FOR CULVERT L WATER DISCHARGE FLOW
4.3.26.
In response to the Condition 2.18 of the Environmental Permit no. EP-356/2009 requiring that a silt curtain /
impermeable barrier system be installed to channel water discharge flow from
Culvert L to locations outside the embayment area, a proposed replacement of
the requirement with additional dissolved oxygen monitoring has been conducted
at three monitoring stations, namely A, B and C between the eastern seawall of Central
Reclamation Phase III and the HKCEC Extension since November 2011 under
EP-356/2009 so that DO level between the eastern seawall of Central Reclamation
Phase II and the HKCEC extension could be continuously monitored.
4.3.27.
With respect
to the commencement of dredging works under HK/2012/08 and the installation of
MTR precast protection unit, the enhanced water quality monitoring for Culvert
L was temporarily suspended since 24 July 2013
4.3.28.
The monitoring of dissolved oxygen are to be carried out once per week,
at mid-flood and mid-ebb tides for 3 water depths (1m below water surface,
mid-depth and 1m above sea bed, except where the water depth less than 6m, the
mid-depth may be omitted. If the water depth be equal to or less than 3m, only
the mid-depth will be monitored).
5.0.1.
The environmental monitoring will be implemented based on the division
of works areas of each designed project managed under different contracts with
separate FEP applied by individual contractors. Overall layout showing work
areas of various contracts, latest status of work commencement and monitoring
stations is shown in Figure 2.1 and Figure 4.1. The monitoring
results are presented in according to the Individual Contract(s).
5.0.2.
In the reporting month, the concurrent contracts are as follows:
Contract
no. HK/2009/02 Wan Chai Development Phase II – Central-Wan Chai Bypass at Wan
Chai East
Contract
no. HY/2009/19- Central- Wan Chai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link
Contract
no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan
Chai West
Contract
no. HY/2010/08 – Central- Wanchai Bypass Tunnel (Slip Road 8 Section)
5.0.3.
As confirmed by WDII RSS, the marine construction works under Contract
HK/2009/01 have been completed since 24 July 2017, the monitoring association
with Contract HK/2009/01 and relevant reporting has been ceased in the
reporting month.
5.0.4.
As confirmed by CWB RSS, the marine construction works under Contract
HY/2009/15 and relevant reporting have been completed by 19 June 2017, the
monitoring association with Contract HY/2009/15 and relevant reporting has been
ceased in the reporting month.
5.0.5.
The environment monitoring schedules for reporting month and coming
month are presented in Appendix 5.1.
Contract no. HK/2009/02 - Wan Chai Development
Phase II – Central – Wan Chai Bypass at WanChai East
5.0.6.
The proposed division of noise monitoring stations are summarized in Table
5.1 below.
Table 5.1 Noise Monitoring Station for Contract nos.
HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Footbridge for Ex-Harbour Road Sports Centre |
5.0.7.
Two limit level exceedances were recorded at M1a – Footbridge for
Ex-Harbour Road Sports Centre on 03 and 22 November 2017.
5.0.8.
Despite excavation works was conducted by Contract HK/2009/02 on 03
November 2017 around the concerned location during the time of measurement
while non WDII-CWB excavation works immediately next to the monitoring station
was observed as the major noise contribution during monitoring with mechanical
operation directly next to noise monitoring position. As such, the exceedance was
considered as non-Project related to Contract HK/2009/02.
5.0.9.
Despite backfilling works was conducted by Contract HK/2009/02 on 22
November around the concerned location with a few, minor and non-continuous
breaking actions under Contractor observed during measurement, acoustic
screening of breaking tip was implemented by Contract HK/2009/02 and no major
noise contribution was observed from the works. Meanwhile, non WDII-CWB
breaking works immediately next to the monitoring station was observed as the
major noise contribution during monitoring. As such, the exceedance was
considered as non-Project related to Contract HK/2009/02. Nevertheless, the
Contractor of HK/2009/02 was reminded to maintain adequate noise mitigation
measure around the concerned location to avoid potential cumulative impact.
5.0.10.
Noise monitoring results measured in this reporting period are reviewed
and summarized. Details of noise monitoring results and graphical presentation
can be referred in Appendix 5.2.
Contract no. HY/2009/19- Wan Chai Bypass Tunnel
(North Point Section) and Island Eastern Corridor Link
5.0.11.
The proposed division of noise monitoring stations are summarized in Table
5.3 below.
Table 5.3 Noise Monitoring Station for Contract no. HY/2009/19
Station |
Description |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist Church Henrietta Secondary School |
5.0.12.
No action or limit level exceedance was recorded in this reporting
month.
5.0.13.
Noise monitoring results measured in this reporting period are reviewed
and summarized. Details of noise monitoring results and graphical presentation
can be referred in Appendix 5.2.
Contract no.
HY/2010/08-Central-Wanchi Bypass Tunnel (Slip Road 8 Section)
5.0.14.
The proposed division of noise monitoring stations are summarized in Table 5.4 below.
Table
5.4 Noise
Monitoring Station for Contract no. HY/2010/08
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
5.0.15.
No action or limit level exceedance was recorded in this reporting
month.
5.0.16.
Noise monitoring results measured in this reporting period are reviewed
and summarized. Details of noise monitoring results and graphical presentation
can be referred in Appendix 5.2.
Contract no. HK/2009/02 - Wan Chai Development
Phase II – Central – Wan Chai Bypass at WanChai East
5.1.1
Air monitoring was commenced in mid-January 2011 for the land-filling
work for Contract no. HK/2009/02. The proposed division of air monitoring
stations are summarized in Table 5.6 below.
Table 5.6 Air
Monitoring Station for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
5.1.2
No action or limit level recorded in this reporting month.
5.1.3
Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.3.
5.1.4
The proposed division of air monitoring stations are summarized in Table
5.8 below.
Table 5.8 Air
Monitoring Stations for Contract no. HY/2009/19
Station |
Description |
CMA1b |
Harbour Grand
Hotel Boundary Wall |
CMA2a |
Causeway Bay
Community Centre |
5.1.5 No action or limit exceedance was
recorded in the reporting month.
5.1.6 Air quality monitoring results
measured in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2012/08- Wan Chai Development Phase
II – Central-Wan Chai Bypass at Wan Chai West
5.1.7
The proposed division of air monitoring stations are summarized in Table
5.9 below.
Table
5.9 Air Monitoring Stations for
Contract no. HK/2012/08
Station |
Description |
CMA5b |
Pedestrian Plaza |
CMA6a |
WDII PRE Site Office |
5.1.8
One 1hr TSP limit level exceedance was recorded at CMA5b – Pedestrian
Plaza on 01 November 2017.
5.1.9
Road and drains works was undertaken under Contract HK/2012/08 on 01
November 2017 around the monitoring location on the monitoring date and no
particular observation regarding air quality impact was observed during
sampling. Mitigation measure including water spraying for haul road was
generally implemented. Nevertheless, non WDII-CWB Project construction activities was observed
opposite to the monitoring station on the monitoring date. Meanwhile, it was
reported that the ambient air quality was adversely affected by accumulation of
air pollutant influenced by the meteorological condition on the monitoring
date. In view of the above, the exceedance was considered to be non-project
related and potentially contributed by ambient air quality condition.
5.1.10
Two 1hr TSP action level exceedances and one 1hr TSP limit level
exceedances were recorded at CMA5b – Pedestrian Plaza on 24 November 2017.
5.1.11
Road and drain construction works was undertaken under Contract
HK/2012/08 on 24 November 2017 around the monitoring location on the monitoring
date and no particular observation regarding air quality impact was observed
during sampling. Mitigation measure including water spraying for haul road was
generally implemented. Nevertheless, non WDII-CWB Project construction
activities was observed opposite to the monitoring station on the monitoring
date. Meanwhile, according to the EPD monitoring record, highest pollutant
concentration was recorded during the monitoring date at Causeway Bay
monitoring station across a seven days period. In view of the above, the
exceedance was considered to be non-project related and potentially contributed
by ambient air quality condition.
5.1.12
Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of
air monitoring results and graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2010/08- Central-Wanchai Bypass
Tunnel (Slip Road 8 Section)
The proposed division of air
monitoring stations are summarized in Table 5.10 below.
Table
5.10 Air Monitoring Stations for Contract
no. HY/2010/08
Station |
Description |
CMA3a |
CWB PRE Site Office |
5.1.13
No action or limit level exceedance was recorded in the reporting month.
Air quality monitoring results measured in this reporting period are reviewed
and summarized. Details of air
monitoring results and graphical presentation can be referred in Appendix 5.3.
5.3.1.
Action and Limit level of water quality monitoring was transited from
wet season to dry season from 1 October 2017.
5.3.2.
Water quality monitoring station C7 and Enhance DO monitoring station C6
shall be associated with Contract HY/2010/08, upon confirmation of marine
construction works completion under Contract HY/2009/15 at CBTS area and
Ex-PCWA area since 19 June 2017.
5.3.3.
Referring to CWB RSS confirmation on the completion of marine
construction activities within the Ex-PCWA area and the completion of the post
construction water quality monitoring, the respective Enhance DO Monitoring
within Ex-PCWA for monitoring station Ex-PCWA SE and Ex-PCWA SW was temporarily
suspended since 07 March 2017 ebb tide onwards.
5.3.4.
With respect to the reinstatement of the silt screen system for Cooling
Water Intakes P7, P8, P9 and WSD Water Intake RW21, the respective water
quality monitoring was reverted to the previous monitoring location for Water
Quality Monitoring Station RW21-P789 from water quality stations RW21-P789 East
(RW21-P789E) and RW21-P789 West (RW21-P789W) from 25 January 2017 onwards.
5.3.5.
With respect to the temporarily suspension of marine construction works
at WCR3 Area by Contract HK/2009/02, the installed silt screen for intake group
(P7, P8, P9 and WSD21) was removed on 26 November 2016.
5.3.6.
As advised by the Contractor of HK/2009/01, all silt screen remains
removal works at P1, P3, P4, P5 and C1 water quality monitoring stations were
completed on 8 May 2016.
5.3.7.
With respect to the marine works undertaken at WCR3 by Contract HK/2009/02,
the respective water quality monitoring station C1 associated with Contract
HK/2009/01 was updated as in association with Contract HK/2009/01 and Contract
HK/2009/02.
5.3.8.
With respect to the marine works undertaken at CBTS by Contract
HY/2010/08, the respective water quality monitoring station C7 associated with
Contract HY/2009/15 was updated as in association with Contract HY/2009/15 and
Contract HY/2010/08.
5.3.9.
With respect to the marine works undertaken at HKCEC2 by Contract HK/2012/08,
the respective water quality monitoring station WSD19, P1, P3, P4, and P5 were
associated with Contract HK/2012/08.
5.3.10.
As confirmed by WDII RSS, the marine construction works under Contract
HK/2009/01 have been completed since 24 July 2017, the monitoring association
with Contract HK/2009/01 and relevant reporting has been ceased in the
reporting month.
5.3.11.
As confirmed by CWB RSS, the marine construction works under Contract HY/2009/15
and relevant reporting have been completed by 19 June 2017, the monitoring
association with Contract HY/2009/15 and relevant reporting has been ceased in
the reporting month.
Table 5.11 Water quality Monitoring
Stations for contracts with respect to remaining DP3 work areas after the
completion of DP5 & DP6 in 2012 and intake diversion in 2013
Contract No. |
Remaining DP3 and work area(s) |
Relevant Water quality monitoring Stations, |
Division of WQM
w.r.t tentative works commenced / to be commenced |
HK/2009/02 |
WCR3, WCR4, TWCR4 |
RW21-P7892, C11 |
Apr 2013 |
HK/2012/08 |
HKCEC2W, HKCEC2E |
WSD19, P13, P33, P43, P53 |
Aug 2013 |
HY/2010/08 |
TCBR3, TCBR4 |
C64, C7 (plus enhanced DO monitoring) |
Mar 2014 |
Remarks:
1. The water quality monitoring station C1 shall be associated with Contract No. HK/2009/02 upon commencement of marine works under DP3 at WCR3 area.
2. 4 intakes (re-provisioned Wanchai WSD intake, Great Eagle Centre, China Resources Centre & Sun Hung Kai Centre constructed adjacent to each other) taken as a single group for silt screen protection and monitoring. Re-provisioned intake reference: P1: HKCEC Phase 1; P3: APA, P4: Shui On; P5: Government Buildings (Wanchai Tower / Revenue Tower / Immigration Tower)
3. The water quality monitoring stations for WSD19, P1, P3, P4, P5 shall be associated with Contract No. HK/2009/01 prior to their transition to Contract HK/2012/08.
4. Enhance DO monitoring station C6 and water quality monitoring station C7 shall be associated with Contract HY/2010/08, upon confirmation of marine construction works completion under Contract HY/2009/15 at CBTS area and Ex-PCWA area since 19 June 2017.
5. With respect to WDII RSS confirmation on the
completion of marine works under Contract HK/2009/01 since 24 July 2017, the
association of WQM station C1 under Contract HK/2009/01 has been ceased in the
November 2017 reporting month.
Contract no. HK/2009/02 - Wan Chai Development Wan
Chai Development Phase II – Central – Wan Chai Bypass at WanChai East
5.3.10 Water quality monitoring for Contract no.
HK/2009/02 was commenced on 8 July 2010. The proposed division of water quality
monitoring stations are summarized in Table 5.13 below.
Table 5.13 Water quality Monitoring Stations for
Contract no. HK/2009/02
Station
Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C1 |
HKCEC
Extension |
835885.6 |
816223.0 |
Cooling Water Intake / WSD Salt
Water Intake |
|||
RW21-P789 |
Great Eagle Centre/ Sun Hung Kai Centre/ WSD Wanchai salt
water intake / China Resources Building |
836268.0 |
816020.0 |
5.3.11
3 action level Turbidity exceedance were recorded at WQM station C1 on
06, 10 and 22 November 2017 and 3 limit level Turbidity exceedances were recorded
at 06, 08 and 20 November 2017.
After checking with the Contractor of
Contract HK/2009/02, no marine construction activity was conducted on 06, 08,
10, 20 and 22 November 2017. In view of no marine construction activity was
conducted during the monitoring date, the exceedances were considered not
related to Project works.
5.3.12
2 action level Turbidity exceedance were recorded at WQM station
RE21-P789 on 17 and 20 November 2017 and limit level Turbidity exceedances were
recorded at RW21-P789 06, 08 and 13 November 2017.
After checking with the Contractor of
HK/2009/02, no marine construction activity was conducted on 06, 08, 13, 17 and
20 November 2017 and the installed silt screen at the RW21-P789 cooling intake
point was observed in order. In view of the above, the exceedance was
considered not project related.
5.3.13
Water quality monitoring results measured in this reporting period are
reviewed and summarized. Details of water quality monitoring results and
graphical presentation can be referred in Appendix 5.4.
Contract
no. HK/2012/08 - Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan
Chai West
5.3.14
Water quality monitoring for Contract no. HK/2012/08 was commenced on 5 March
2013. The proposed division of water quality monitoring stations are summarized
in Table 5.14 below.
Table 5.14 Water quality Monitoring Stations for
Contract no. HK/2012/08
Station Ref. |
Location |
Easting |
Northing |
|
WSD Salt Water Intake |
||||
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
|
Cooling Water
Intake |
||||
P1 |
HKCEC
Phase I |
835774.7 |
816179.4 |
|
P3 |
The Academy of performing Arts |
835824.6 |
816212.0 |
|
P4 |
Shui on Centre |
835865.6 |
816220.0 |
|
P5 |
Government Buildings (Wanchai Tower / Revenue Tower / Immigration
Tower) |
835895.2 |
816215.2 |
|
5.3.15
5 action level Turbidity exceedances were recorded at WQM station WSD19
on 27, 30 October 2017 06 and 17 November 2017 and 7 limit level Turbidity
exceedances were recorded at WQM station WSD19 on 08, 10, 13, 20 and 24
November 2017.
3 limit level Suspended Solid
exceedances were recorded at WQM station WSD19 on 03, 08 and 17 November 2017.
After checking with Contractor of
HK/2012/08, either no marine construction works or installation of seawall
block or trimming of rock level within silt curtain enclosure were conducted on
aforementioned monitoring dates and no water quality impact were considered. Therefore,
the exceedances were considered as not related to the Project work.
5.3.16
2 action level turbidity exceedances were recorded at WQM station P1 on
06 and 08 November 2017.
After checking with Contractor of HK/2012/08,
trimming of rock level was conducted within silt curtain enclosure on the above
monitoring dates and no particular water quality impact was considered.
Therefore, the exceedances were considered as not related to the Project work.
5.3.17
2 action level Turbidity exceedances were recorded at WQM statin P3 on
06, 20 November 2017 and 1 limit level Turbidity exceedances were recorded at
WQM station P3 on 06 November 2017.
After checking with Contractor of
HK/2012/08, trimming of rock level was conducted within silt curtain enclosure
on the above monitoring dates and no particular water quality impact was
considered. Therefore, the exceedances were considered as not related to the
Project work.
5.3.18
1 limit level exceedance Turbidity exceedance was recorded at WQM
station P4 on 10 November 2017 and 1 action level Suspended Solid exceedance
was recorded on 08 November 2017.
After checking with Contractor of
HK/2012/08, trimming of rock level was conducted within silt curtain enclosure
on the above monitoring dates and no particular water quality impact was
considered. Therefore, the exceedances were considered as not related to the
Project work.
5.3.19
3 action level Turbidity exceedances were recorded at WQM station P5 on
06, 13 and 20 November 2017 and 1 limit level exceedance was recorded at WQM
station P5 on 08 November 2017.
After checking with Contractor of
HK/2012/08, trimming of rock level was conducted within silt curtain enclosure
on the above monitoring dates and no particular water quality impact was
considered. Therefore, the exceedances were considered as not related to the
Project work.
5.3.20
Water quality monitoring results measured in this reporting period are
reviewed and summarized. Details of water quality monitoring results and
graphical presentation can be referred in Appendix 5.4.
Contract
no. HY/2010/08- Central-Wanchai Bypass Tunnel (Slip Road 8 Section)
5.3.21
The proposed division of water quality monitoring stations are
summarized in Table 5.15 and Table
5.16 below:
Table 5.15 Water quality monitoring Stations
for Contract no. HY/2010/08
Station
Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C7 |
Windsor
House |
837193.7 |
816150.0 |
Table 5.16 Enhance Dissolved Oxygen Monitoring Stations for Contract no.
HY/2010/08
Station
Ref. |
Location |
C6 |
Excelsior
Hotel |
Remarks: Enhanced DO
monitoring at Windsor House Cooling (Station Ref: C7) was temporarily
suspended since 22 October 2014 with respect to the
formation of temporary reclamation zone TS3 and
to be resumed upon removal of the respective temporary
reclamation zone.
5.3.22
2 limit level Turbidity exceedance at WQM station C7 were recorded on 27
October 2017 and 03 November 2017.
5.3.23
After checking with Contractor of HY/2010/08, no construction works was
conducted on 27 October 2017 while seabed reinstatement works was conducted on
03 November 2017 and mitigation measure including deployment of frame type silt
curtain around the works area and provision of silt screen at the water intake
point were in order. Therefore, the exceedances were considered not related to
Project works.
5.3.24
Water quality monitoring results measured in this reporting period are
reviewed and summarized. Details of water quality monitoring results and
graphical presentation can be referred in Appendix 5.4.
Contract no. HK/2009/01 - Wan Chai Development Phase
II – Central –Wanchai Bypass at HKCEC
5.4.1.
No inert C&D waste and non- inert C&D waste disposed in this
reporting month. Details of the waste flow table are summarized in Table
5.17.
Table 5.17 Details of Waste
Disposal for Contract no. HK/2009/01
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
NIL |
62116.405 |
TKO137, TM38 |
Inert C&D materials recycled, m3 |
NIL |
5856.5 |
N/A |
Non-inert C&D materials disposed, m3 |
NIL |
1673.69 |
SENT Landfill |
Non-inert C&D materials recycled, kg |
NIL |
203993 |
N/A |
Chemical waste disposed, kg |
NIL |
10250 |
N/A |
Marine Sediment (Type 1 – Open Sea Disposal), m3 |
NIL (Bulk Volume) |
97428.2 (Bulk Volume) |
South of Cheung Chau |
Marine Sediment (Type 1 – Open Sea Disposal
(Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3 |
NIL (Bulk Volume) |
52250 (Bulk Volume) |
East of Cha Chau |
Dredged Sediment
Requiring Type 3 – Special Treatment / Disposal contained in Geosynthetic
Containers |
NIL (Bulk Volume) |
6773 (Bulk Volume) |
East of Cha Chau |
5.4.2.
No marine sediment Type 1- Open Sea Disposal and no marine sediments
Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine
Disposal disposed in this
reporting month.
Contract no. HK/2009/02 - Wan Chai Development
Phase II – Central – Wan Chai Bypass at Wan Chai East
5.4.3.
No inert C&D waste and Non-inert C&D waste disposed of in this
reporting month. Details of the waste flow table are summarized in Table
5.18.
Table 5.18 Details of Waste
Disposal for Contract no. HK/2009/02
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
NIL |
276075.1 |
TKO137 / TM 38 |
Inert C&D materials recycled, m3 |
NIL |
18161 |
N/A |
Non-inert C&D materials disposed, m3 |
NIL |
1515.103 |
SENT Landfill |
Non-inert C&D materials recycled, m3 |
N/A |
N/A |
N/A |
Chemical waste disposed, kg |
NIL |
13860 |
SENT Landfill |
Marine Sediment (Type 1 – Open Sea Disposal), m3
|
NIL |
240222 (Bulk volume) |
South of Cheung Chau |
Marine Sediment (Type 1 – Open Sea Disposal
(Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3 |
NIL |
146445 (Bulk volume) |
East of Sha Chau |
5.4.4.
There were no marine sediment Type 1 – Open Sea Disposal and no Type 1
Open Sea Disposal (Dedicate Sties) & Type 2 – Confined Marine Disposal disposed in this reporting month.
Contract no. HY/2009/15 - Central-Wanchai Bypass –
Tunnel (Causeway Bay Typhoon Shelter Section)
5.4.5.
No Inert and non-inert C&D material was recycled in this reporting month.
Details of the waste flow table are summarized in Table 5.19
Table 5.19 Details of Waste
Disposal for Contract no. HY/2009/15
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Remarks |
Inert C&D materials disposed, m3 |
NIL |
141579.2 |
Tuen Mun Area 38 |
NIL |
NIL |
65216 |
TKO137 FB |
NIL |
|
Inert C&D materials recycled, m3 |
NIL |
8127.21 |
HY/2010/08 |
NIL |
NIL |
304 |
Ex-PCWA |
NIL |
|
NIL |
111.9 |
TS4 |
NIL |
|
Non-inert C&D materials disposed, m3 |
NIL |
252.2 |
SENT Landfill |
NIL |
Non-inert C&D materials recycled, kg |
NIL |
299361.5 |
N/A |
NIL |
Chemical waste disposed, kg |
NIL |
8,200 |
N/A |
NIL |
Marine Sediment (Type 1 – Open Sea Disposal), m3 |
NIL (Bulk Volume) |
156909 (Bulk Volume) |
Cheung Chau South |
Dredging from TCBR1E / TCBR1W / TCBR2/ TCBR3 /
TCBR4 / Maintenance dredging |
Marine Sediment (Type 1 – Open Sea Disposal
(Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3 |
NIL (Bulk Volume) |
327746 (Bulk Volume) |
East of Sha Chau / South of the Brothers |
Dredging from TCBR1E / TCBR1W / TCBR2/ TCBR3 /
TCBR4 / Maintenance dredging |
Marine
Sediment (Type 3 – Special Treatment / Disposal contained in Geosynthetic
Containers) m3 |
NIL (Bulk Volume) |
12640 (Bulk Volume) |
East of Sha Chau / South of the Brothers |
Dredging from TCBR1W / Maintenance dredging |
Marine
Sediment (Type 2 – Confined Marine Disposal), m3 |
NIL |
9350 (Bulk Volume) |
East of Sha Chau |
Dredging from Eastern Breakwater of CBTS |
Marine Sediment (Type 1 – Open Sea Disposal)
, m3 |
NIL (Bulk Volume) |
600 (Bulk Volume) |
East Sha Chau / South of The Brothers |
Dredging from Phase 3
Mooring Re-arrangement |
Marine Sediment (Type 2– Confined Marine Disposal)
, m3 |
NIL (Bulk Volume) |
14,780 (Bulk Volume) |
South of The Brothers |
Dredging from Phase 3
Mooring Re-arrangement |
Marine Sediment (Type 3 – Special Treatment /
Disposal contained in Geosynehetic Containers) , m3 |
NIL (Bulk Volume) |
2,760 (Bulk Volume) |
South of The Brothers |
Dredging from Phase 3
Mooring Re-arrangement |
5.4.6.
No Type 1 Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine Disposal and Type 1 Open Sea Disposal disposed in
this reporting month.
Contract no. HY/2009/19 –Central- WanChai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
5.4.7.
No inert C&D waste and non-inert C&D waste disposed in this
reporting month. Details of the waste flow table are summarized in Table
5.20.
Table 5.20 Details of Waste Disposal for
Contract no. HY/2009/19
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
NIL |
355921.04 |
TM38 |
Inert C&D materials recycled, m3 |
NIL |
59367 |
N/A |
Non-inert C&D materials disposed, m3 |
NIL |
1068.6 |
N/A |
Non-inert C&D materials recycled, kg |
NIL |
333.14 |
N/A |
Chemical waste disposed, L |
NIL |
2.12 |
N/A |
Marine Sediment (Type 1 – Open Sea Disposal), m3 |
NIL |
162 |
South Cheung Chau |
Marine Sediment (Type 2 – Confined Marine
Disposal) , m3 |
NIL |
681 |
East Sha Chau |
Marine Sediment (Type 1 – Open Sea Disposal
(Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3 |
NIL |
4976.00 |
East Sha Chau |
Contract no. HK/2012/08 –Wan Chai Development Phase
II – Central- Wan Chai Bypass at Wan Chai West
5.4.9.
There was no Inert C&D waste and no non-inert C&D waste was disposed
in this reporting month. Details of the waste flow table are summarized in Table
5.21.
Table 5.21 Details of Waste Disposal for Contract no. HK/2012/08
Waste Type |
Quantity
this month |
Cumulative
Quantity-to-Date |
Disposal
/ Dumping Grounds |
Inert C&D materials disposed, m3 * |
NIL |
4131 |
TM38 |
|
NIL |
273 |
TKO137 |
Inert C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed, m3 |
NIL |
400 |
SENT |
Non-inert C&D materials recycled, kg |
NIL |
NIL |
N/A |
Chemical waste disposed, L |
NIL |
NIL |
N/A |
Marine Sediment (Type 1 – Open Sea Disposal), m3 |
NIL (Bulk
volume) |
31759 (Bulk
volume) |
South
of Cheung Chau |
Marine Sediment (Type 1 – Open Sea Disposal
(Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3 |
NIL (Bulk
volume) |
108542 (Bulk
volume) |
South
of The Brothers (from 27 Aug 2013 onwards) |
5.4.10.
No Marine Sediment Type 1 – Open Sea Disposal (Delicate Sites) &
Type 2 – Confined Marine Disposal and Marine Sediment Type 1 – Open Sea
Disposal disposed in this reporting month.
Contract
no. HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip Road 8)
5.4.11.
No Inert C&D waste was disposed in this reporting month and no non-inert
C&D waste disposed in this reporting month. Details of the waste flow table
are summarized in Table 5.22
Table 5.22 Details of Waste Disposal for Contract no. HY/2010/08
Waste Type |
Quantity
this month |
Cumulative
Quantity-to-Date |
Disposal
/ Dumping Grounds |
Inert C&D materials disposed, m3 |
NIL NIL |
91432.537 19739.4 |
TM38 TKO137 |
Inert C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed, m3 |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled, kg |
NIL |
NIL |
N/A |
Chemical waste disposed, L |
NIL |
NIL |
N/A |
Marine Sediment (Type 1 – Open Sea Disposal) |
NIL |
62559.4 |
South Cheung Chau / Brothers Island * |
Marine Sediment (Type 1 – Open Sea Disposal (Dedicate
Sites) & Type 2 – Confined Marine disposal) |
NIL |
28309.2 |
Brothers Island |
Marine Sediment (Type 3 – Special Treatment) |
NIL |
7780 |
Brothers Island |
5.4.12.
No Type 1 – Open Sea Disposal and no Type 1 – Open Sea Disposal
(Dedicate Sites) & Type 2 – Confined Marine Disposal disposed in this reporting
month, and no Type 3- Special Treatment disposed in this reporting month.
6.0.1.
The Event Action Plan for construction noise, air quality and water
quality are presented in Appendix 6.1.
Contract no.
HK/2009/02 - Wan Chai Development Phase II – Central – Wan Chai Bypass at WanChai
East
6.1.1
No action or limit level exceedance was recorded in this reporting
month.
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link
6.1.2
No exceedance was recorded in the reporting month.
Contract no. HY/2010/08
– Central-Wanchai Bypass – Tunnel (Slip Road 8
Section)
6.1.3
No exceedance was recorded in the reporting month.
Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai East (CWB Tunnel)
6.2.1
No action or limit level exceedance was recorded in this reporting
month.
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link
6.2.2
No action or limit level exceedance was recorded in this reporting
month.
Contract no. HK/2012/08 Wan Chai Development Phase II -
Central-Wan Chai Bypass at Wan Chai West
6.2.3
One 1hr TSP action level exceedance was recorded at CMA5b – Pedestrian
Plaza on 01 November 2017 in the reporting month and the exceedance was
concluded as non-Project related.
6.2.4
Two 1hr TSP action level exceedances and one 1hr TSP limit level were
recorded at CMA5b – Pedestrian Plaza on 24 November 2017 in the reporting month
and the exceedance was concluded as non-Project related.
Contract no. HY/2010/08 – Central-Wanchai Bypass –
Tunnel (Slip Raod 8 Section)
6.2.5
No action or limit level exceedance was recorded in the reporting month.
Contract no. HK/2009/02 - Wan Chai Development Phase II – Central – Wan
Chai Bypass at WanChai East
6.3.1
3 action level Turbidity exceedance were recorded at WQM station C1 on
06, 10 and 22 November 2017 and 3 limit level Turbidity exceedances were recorded
at 06, 08 and 20 November 2017.
After
checking with the Contractor of Contract HK/2009/02, no marine construction
activity was conducted on 06, 08, 10, 20 and 22 November 2017. In view of no
marine construction activity was conducted during the monitoring date, the
exceedances were considered not related to Project works.
6.3.2
2 action level Turbidity exceedance were recorded at WQM station
RE21-P789 on 17 and 20 November 2017 and limit level Turbidity exceedances were
recorded at RW21-P789 06, 08 and 13 November 2017.
After
checking with the Contractor of HK/2009/02, no marine construction activity was
conducted on 06, 08, 13, 17 and 20 November 2017 and the installed silt screen
at the RW21-P789 cooling intake point was observed in order. In view of the
above, the exceedance was considered not project related.
Contract no. HY/2009/19- Central- Wan Chai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link
6.3.3
No action or limit level exceedance was recorded in this reporting
month.
Contract no. HK/2012/08- Wan Chai Development Phase II – Central- Wan
Chai Bypass at Wan Chai West
6.3.4
5 action level Turbidity exceedances were recorded at WQM station WSD19
on 27, 30 October 2017 06 and 17 November 2017 and 7 limit level Turbidity
exceedances were recorded at WQM station WSD19 on 08, 10, 13, 20 and 24
November 2017.
3 limit
level Suspended Solid exceedances were recorded at WQM station WSD19 on 03, 08
and 17 November 2017.
After
checking with Contractor of HK/2012/08, either no marine construction works or
installation of seawall block or trimming of rock level within silt curtain
enclosure were conducted on aforementioned monitoring dates and no water
quality impact were considered. Therefore, the exceedances were considered as not
related to the Project work.
6.3.5
2 action level turbidity exceedances were recorded at WQM station P1 on
06 and 08 November 2017.
After
checking with Contractor of HK/2012/08, trimming of rock level was conducted
within silt curtain enclosure on the above monitoring dates and no particular
water quality impact was considered. Therefore, the exceedances were considered
as not related to the Project work.
6.3.6
2 action level Turbidity exceedances were recorded at WQM statin P3 on
06, 20 November 2017 and 1 limit level Turbidity exceedances were recorded at
WQM station P3 on 06 November 2017.
After
checking with Contractor of HK/2012/08, trimming of rock level was conducted
within silt curtain enclosure on the above monitoring dates and no particular
water quality impact was considered. Therefore, the exceedances were considered
as not related to the Project work.
6.3.7
1 limit level exceedance Turbidity exceedance was recorded at WQM
station P4 on 10 November 2017 and 1 action level Suspended Solid exceedance
was recorded on 08 November 2017.
After
checking with Contractor of HK/2012/08, trimming of rock level was conducted
within silt curtain enclosure on the above monitoring dates and no particular
water quality impact was considered. Therefore, the exceedances were considered
as not related to the Project work.
6.3.8
3 action level Turbidity exceedances were recorded at WQM station P5 on
06, 13 and 20 November 2017 and 1 limit level exceedance was recorded at WQM
station P5 on 08 November 2017.
After
checking with Contractor of HK/2012/08, trimming of rock level was conducted
within silt curtain enclosure on the above monitoring dates and no particular
water quality impact was considered. Therefore, the exceedances were considered
as not related to the Project work.
Contract no. HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip
Road 8)
6.3.9
2 limit level Turbidity exceedance at WQM station C7 were recorded on 27
October 2017 and 03 November 2017.
After
checking with Contractor of HY/2010/08, no construction works was conducted on
27 October 2017 while seabed reinstatement works was conducted on 03 November
2017 and mitigation measure including deployment of frame type silt curtain
around the works area and provision of silt screen at the water intake point
were in order. Therefore, the exceedances were considered not related to
Project works
6.4.1
There was no non-compliance from the site audits in the reporting
period. The observations and recommendations made in each individual site audit
session were presented in Section 8.
6.5.1
No particular action taken was taken for site audits since no
non-compliance was recorded in the reporting period.
7.0.1.
According to Condition 3.4 of the EP-356/2009, this section addresses
the relevant cumulative construction impact due to the concurrent activities of
the current projects including the Central Reclamation Phase III,
Central-Wanchai Bypass and Island Eastern Corridor Link projects.
7.0.2. According to the Final EM&A Report of Central Reclamation Phase III (CRIII) for Contract HK 12/02,
the major construction activities were completed by end of January 2014 and no
construction activities were undertaken thereafter and the water quality
monitoring was completed in October 2011 and no Project-related exceedance was
recorded for air and noise monitoring.
It can be concluded that cumulative construction impact due to the
concurrent activities of the current projects with the Central Reclamation
Phase III (CRIII) was insignificant.
7.0.3.
According to the construction programme of Central-Wanchai Bypass at
Wanchai West at the Central Reclamation Phase III area include road and drain
works, backfilling works and reinstatement of culvert, trimming of rock levels
and cooling mains and reinstatement of planter at P1 road were performed in
October 2017 reporting period. As no project related exceedance were
recorded during the reporting period, cumulative construction impact due to the
concurrent activities of the current projects with the Central Reclamation
Phase III (CRIII) was considered as insignificant.
7.0.4. According to the construction programme of Wan Chai
Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link
projects, the major construction activities under Wan Chai Development Phase II
were road and drains construction, tunnel construction and backfilling works at
Wan Chai West and Wan Chai East. The major construction activities under
Central-Wan Chai Bypass and Island Eastern Corridor Link Projects were drainage
works and ventilation building construction at Central; temporary reclamation
removal works at Causeway Bay, road works and side wall construction at
Victoria Park; bridge construction, piling works, foundation works and building
construction at North Point area in the reporting period. In addition, other
non-Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern
Corridor Link projects was observed undertaken at Wan
Chai North and North Point area.
7.0.5. No significant air impact from
construction activities was anticipated in the reporting month. Besides, no
project related exceedance was recorded during the air and noise environmental
monitoring events in the reporting month. Thus, it is evaluated that the
cumulative construction impact from the concurrent projects including Central
Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII),
Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) was
insignificant.
8.0.1. During this reporting month,
weekly environmental site audits were conducted for Contracts no. HK/2009/01, HK/2009/02, HY/2009/15,
HY/2009/19, HK/2012/08 and HY/2010/08. No non-conformance was identified during
the site audits.
8.0.1. Site inspections for Contract no.
HK/2009/01 were conducted in reporting month. No observation was found in the reporting
period
8.0.2. Site inspection for Contract no.
HY/2009/15 was conducted in reporting month. No observation was found in the
reporting period
8.0.3. Site inspections for Contract no.
HK/2009/02 were conducted in reporting month. Results of these inspections and
outcomes are summarized in Table 8.2.
Table 8.2 Summary of
Environmental Inspections for Contract no. HK/2009/02
Item |
Date |
Observations |
Action taken
by Contractor |
Outcome |
171102_01 |
3 Nov 2017 |
Water
spraying shall be implement frequently at Portion 5. |
Water
spraying has been provided for dusty surface |
Completion
as observed on 09 November 2017 |
171109_01 |
9 Nov 2017 |
Wheel
washing at Gate 6 shall be strengthen to avoid muddy trail on the public
road. |
Wheel
washing operation has been improved and no further muddy trail was observed |
Completion
as observed on 16 November 2017 |
171116_01 |
16 Nov
2017 |
Contractor
shall ensure the dust mitigation to breaking works (Hung Hing
Road Temporary Bridge) |
No further
dust emission was observed |
Completion
as observed on 21 November 2017 |
8.0.4.
Site inspections for Contract no. HY/2009/19 were carried out in
reporting month. There was no particular findings observed in this reporting
month. The results of these inspections and
outcomes are summarized in Table 8.3.
Table 8.3 Summary of
Environmental Inspections for Contract no. HY/2009/19
Item |
Date |
Observations |
Action
taken by Contractor |
Completion
date |
171122_01 |
22 Nov 2017 |
Damaged temporary noise barriers
shall be repair (Oil Street) |
Damaged temporary noise barriers
was repaired |
Completion as observed on 6
December 2017 |
8.0.5. Site inspections for Contract no.
HK/2012/08 were carried out in this reporting period. Results of these
inspections and outcomes are summarized in Table
8.5.
Table 8.5 Summary of Environmental Inspections for Contract
no. HK/2012/08
Item |
Date |
Observations |
Action
taken by Contractor |
Outcome |
171107_01 |
7-Nov-17 |
The condition of site hoarding
shall be improve to avoid potential dust emission (Lung King Street) |
The condition of site hoarding was
improved |
Completion as observed on 14
November 2017 |
8.0.6. Site inspections for Contract no. HY/2010/08
were conducted in this reporting period. Results of these inspections and
outcomes are summarized in Table 8.6.
Table 8.6 Summary of Environmental Inspections for Contract
no. HY/2010/08
Item |
Date |
Observations |
Action
taken by Contractor |
Outcome |
171122_01 |
22-Nov-17 |
Contractor shall provide regular
maintenance to excavator to avoid dark smoke emission (Victoria Park) |
The concerned excavator was
repaired and no further dark smoke emission was observed |
Completion as observed on 29
November 2017 |
9.0.1.
No environmental complaint received in this reporting month.
9.0.2.
The details of cumulative complaint log and updated summary of
complaints are presented in Appendix
9.1
9.0.3.
Cumulative statistic on complaints and successful prosecutions are
summarized in Table 9.1 and Table 9.2 respectively.
Table 9.1 Cumulative
Statistics on Complaints
Reporting Period |
No. of Complaints |
Commencement works (Mar 2010) to last
reporting month |
47 |
November 2017 |
0 |
Total |
47 |
Table 9.2 Cumulative
Statistics on Successful Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this month (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
10.0.1.
The EM&A programme was carried out in accordance with the EM&A
Manual requirements, minor alterations to the programme proposed were made in
response to changing circumstances.
10.0.2.
The scheduled construction activities and the recommended mitigation
measures for the coming month are listed in Table 10.1.
Table 10.1 Construction
Activities and Recommended Mitigation Measures in
Coming Reporting Month
Contract No. |
Key Construction Works |
Recommended Mitigation Measures |
HK/2009/01 |
·
Nil |
·
Nil |
HK/2009/02 |
·
Nil |
·
Daily visual inspection of silt screen and
silt curtain to ensure its operation properly. ·
Implement silt curtain in accordance with the
associated plans submitted to EPD. |
HY/2009/15 |
·
Nil |
·
Nil |
HY/2009/19 |
·
Nil |
·
Nil |
HK/2012/08 |
·
Construction of Box 1 unit and
backfilling |
·
To conform the installation and setting as in
the silt screen and silt curtain deployment plan ·
To space out noisy
equipment and position as far as possible from sensitive receiver. ·
Daily visual inspection of silt screen and
silt curtain to ensure its operation properly |
HY/2010/08 |
·
Diversion pipe maintenance ·
Diaphragm Wall Removal Works ·
Removal of reclamation at TS3E and
TS3W |
·
To conform the installation and setting as in
the silt screen and silt curtain deployment plan ·
Daily visual inspection of silt screen and
silt curtain to ensure its operation properly |